Construction Project Cost Control Quiz

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the amount the job is over budget by after spending 4,700 mhrs?

  • 1,600 mhrs (correct)
  • 2,500 mhrs
  • 1,200 mhrs
  • 2,100 mhrs

What percentage of the job's total scope was completed after 6 months?

  • 52% of 96 units (correct)
  • 50 units
  • 55% of 96 units
  • 45 units

How much money was the project under budget after 6 months, given the budget of $12 million and $5 million spent?

  • $1.25 million (correct)
  • $1 million
  • $2 million
  • $2.5 million

How far behind schedule is the job after 4.3 months, given a planned completion of 2.5 months for the completed work?

<p>1.8 months (D)</p> Signup and view all the answers

What does a CPI (Cost Performance Index) less than 1 indicate about a project?

<p>The project is over budget (A)</p> Signup and view all the answers

What does an SPI (Schedule Performance Index) greater than 1 indicate about a project?

<p>The project is ahead of schedule (B)</p> Signup and view all the answers

Which of the following describes 'Actual Cost of Work Performed' (ACWP)?

<p>The actual expenditures for completed work at a specific time (B)</p> Signup and view all the answers

Which formula correctly reflects how to calculate the total earned value (BCWP) for the project based on percent complete?

<p>Percent complete * Total contract (A)</p> Signup and view all the answers

What does a cost variance (CV) greater than zero indicate?

<p>The project is under budget. (D)</p> Signup and view all the answers

How is schedule variance (SV) calculated?

<p>SV = BCWP – BCWS (D)</p> Signup and view all the answers

In the context of earned value management, what does an SPI greater than 1.0 signify?

<p>The project is ahead of schedule. (B)</p> Signup and view all the answers

What does a Cost Performance Index (CPI) of 1.25 imply about the project's performance?

<p>For every dollar spent, $1.25 worth of work is accomplished. (A)</p> Signup and view all the answers

If a project has a BCWP of $6,250,000 and a BCWS of $6,000,000, what is the schedule variance (SV)?

<p>$250,000 (C)</p> Signup and view all the answers

Which of the following correctly defines the term 'ACWP'?

<p>Actual Cost of Work Performed (B)</p> Signup and view all the answers

If the project scope is 96 units at a cost of $12 million, what is the cost per unit?

<p>$125,000 (B)</p> Signup and view all the answers

What does a negative cost variance (CV) indicate about a project's financial status?

<p>The project is underperforming and over budget. (B)</p> Signup and view all the answers

What is the projected cost of completing the brick laying job?

<p>$22,500 (C)</p> Signup and view all the answers

What is the target unit cost of the bricks remaining to be installed?

<p>$1.83/brick (B)</p> Signup and view all the answers

Which of the following is NOT an objective of project control?

<p>Increase the project budget (D)</p> Signup and view all the answers

After 4.3 months, how many man-hours have been spent on the job if 4,700 man-hours have been recorded?

<p>4,700 mhrs. (D)</p> Signup and view all the answers

What percent complete is the job if 12,500 sq.ft. is in place out of 40,000 sq.ft.?

<p>31% (B)</p> Signup and view all the answers

Which of the following describes the trend in productivity over the course of a job?

<p>Starts slow, picks up speed, and slows down near the end (B)</p> Signup and view all the answers

Which approach is used to take corrective action during the job?

<p>Allocate resources differently (D)</p> Signup and view all the answers

What is the unit cost of the carpenter man-hours required to complete the formwork job?

<p>0.25 mhrs./sq.ft. (D)</p> Signup and view all the answers

What does EAC stand for in project forecasting?

<p>Estimated Cost at Completion (C)</p> Signup and view all the answers

What is the formula for calculating Estimated Cost at Completion (EAC)?

<p>EAC = ACWP + (BAC - BCWP) (C)</p> Signup and view all the answers

If the Schedule Performance Index (SPI) is calculated as 1.14, what does this indicate about the project's schedule?

<p>The project is ahead of schedule. (C)</p> Signup and view all the answers

What is the Cost Performance Index (CPI) if the Cost Variance is -$100 and BCWP is $1,900?

<p>0.95 (C)</p> Signup and view all the answers

What will be the Estimated Cost at Completion (EAC) given the values: ACWP = $2,000, BAC = $3,200, and BCWP = $1,900?

<p>$3,300 (D)</p> Signup and view all the answers

What is the primary purpose of cost control in construction projects?

<p>To maintain expenditure within the authorized estimate while ensuring quality (A)</p> Signup and view all the answers

How is estimated cost defined in a construction project?

<p>The initial budget that serves as a benchmark for measuring progress (C)</p> Signup and view all the answers

What action should a project manager take if the actual cost exceeds the estimated cost?

<p>Analyze the cause of the cost overruns for corrective action (D)</p> Signup and view all the answers

What are actual costs in the context of project management?

<p>The costs that have been incurred during the construction process (A)</p> Signup and view all the answers

What is the difference between projected cost and target cost?

<p>Projected cost is an updated estimate based on actuals, while target cost is the desired expenditure (D)</p> Signup and view all the answers

What might indicate that actual costs are lower than estimated costs?

<p>Improved worker productivity or inaccurate estimates could be reasons (B)</p> Signup and view all the answers

Which of the following best defines unit cost?

<p>The cost associated with a single unit of measure like a brick or worker-hour (B)</p> Signup and view all the answers

Which of the following is NOT a type of cost in construction projects?

<p>Indicator cost (B)</p> Signup and view all the answers

Flashcards

Project Cost Control

Managing construction expenditures to stay within the budget, ensuring desired quality and timely completion.

Estimated Cost

Pre-determined cost for a project job, used as a benchmark.

Actual Cost

The real cost incurred during project execution.

Projected Cost

Forecasted total cost of a job, based on current actual cost and progress.

Signup and view all the flashcards

Cost Performance

Measured by comparing actual cost to the expected cost for a project.

Signup and view all the flashcards

Project Performance

A function of schedule and cost performance.

Signup and view all the flashcards

Unit Cost

Cost per unit of output or material.

Signup and view all the flashcards

Target Cost

The desired cost outcome, frequently used as a goal for cost reduction.

Signup and view all the flashcards

Project Control Elements

Key aspects of managing a project, including Scope, Budget, and Schedule.

Signup and view all the flashcards

Project Control Objectives

Goals of project control, like creating historical data, comparing actual to estimated, and motivating team members during project execution.

Signup and view all the flashcards

Cost and Schedule Analysis

Evaluates project progress against estimated costs and timelines at a specific point in time.

Signup and view all the flashcards

Analyzing Project Progress

Assessing the project's current state based on the actual progress made with respect to scheduled and cost estimations.

Signup and view all the flashcards

Project Progress Measurement

Tracking the actual progress of a project against its plan.

Signup and view all the flashcards

Corrective Action

Steps taken to address deviations from the project plan to bring it back on track.

Signup and view all the flashcards

Cost Performance Index (CPI)

A ratio that measures how efficiently a project is being completed relative to its budget. A value greater than 1 indicates the project is under budget, a value less than 1 signifies it's over budget.

Signup and view all the flashcards

Schedule Performance Index (SPI)

A ratio that indicates how a project is progressing against its schedule. An SPI greater than 1 means the project is ahead of schedule, while an SPI less than 1 indicates it's behind schedule.

Signup and view all the flashcards

Earned Value (EV)

The budgeted cost associated with work actually completed in a project at a given point in time.

Signup and view all the flashcards

Actual Cost of Work Performed (ACWP)

The actual expenses incurred for tasks that have been completed during a project at a particular time.

Signup and view all the flashcards

Budgeted Cost of Work Performed (BCWP)

The budget amount associated with the completed work on a project.

Signup and view all the flashcards

Planned Value (PV)

The budgeted value of the tasks scheduled for completion at a given time in the project.

Signup and view all the flashcards

Project % Complete

The percentage of the project scope that has been completed at a given time.

Signup and view all the flashcards

What is EAC?

Estimated Cost at Completion (EAC) is a forecast of the total cost of a project, considering both current actual cost and the remaining work.

Signup and view all the flashcards

What does BCWP stand for?

BCWP stands for Budgeted Cost of Work Performed. This is the value of the work completed to date, based on the project budget.

Signup and view all the flashcards

What is Schedule Variance?

Schedule Variance is a measure of how much ahead or behind schedule a project is. It's calculated as the difference between BCWP and BCWS.

Signup and view all the flashcards

What is CPI?

Cost Performance Index (CPI) compares the actual cost of work done to the budgeted cost. It shows how efficiently the project is using its budget.

Signup and view all the flashcards

What does SPI represent?

Schedule Performance Index (SPI) shows how well the project is progressing in terms of schedule. It compares the value of work done to the planned work.

Signup and view all the flashcards

CV (Cost Variance)

Measures the difference between the budgeted cost of work performed (BCWP) and the actual cost of work performed (ACWP). Positive CV means under budget, negative CV means over budget.

Signup and view all the flashcards

SV (Schedule Variance)

Measures the difference between the budgeted cost of work performed (BCWP) and the budgeted cost of work scheduled (BCWS). Positive SV means ahead of schedule, negative SV means behind schedule.

Signup and view all the flashcards

CPI (Cost Performance Index)

Calculates the efficiency of spending. It's the ratio of the budgeted cost of work performed (BCWP) to the actual cost of work performed (ACWP). CPI > 1 indicates under budget, CPI < 1 indicates over budget.

Signup and view all the flashcards

SPI (Schedule Performance Index)

Measures the schedule efficiency. It's the ratio of the budgeted cost of work performed (BCWP) to the budgeted cost of work scheduled (BCWS). SPI > 1 indicates ahead of schedule, SPI < 1 indicates behind schedule.

Signup and view all the flashcards

BCWP (Budgeted Cost of Work Performed)

Represents the value of the work completed based on the budget. It's calculated by multiplying the percentage of work completed by the total budget for the project.

Signup and view all the flashcards

ACWP (Actual Cost of Work Performed)

Represents the actual cost incurred for the work that has been completed. It's the real cost spent.

Signup and view all the flashcards

BCWS (Budgeted Cost of Work Scheduled)

Represents the value of the work that was planned to be completed by a certain point in time based on the budget.

Signup and view all the flashcards

Estimate At Completion (EAC)

The projected total cost of the project, taking into account past performance and remaining work. It is used to forecast the final cost.

Signup and view all the flashcards

Study Notes

Project Cost Control

  • Cost control is defined as managing expenditures within the authorized budget, ensuring desired quality, and timely completion.
  • Essential for profitable construction projects.
  • Construction managers need to be aware of and control project costs.
  • Three main types of costs in construction projects: estimated, actual, and projected/target costs.

Estimated Cost

  • Defines the initial budget for a project.
  • Often presented as either a total direct cost for a job or a unit price based on material quantity.
  • Sets the limit for spending on a project.

Actual Cost

  • Costs incurred during project execution.
  • Tracking actual costs is crucial for monitoring and controlling potential cost overruns.
  • Regular cost tracking during construction is important.
  • Discrepancies between actual and estimated costs should trigger corrective actions by project managers.

Projected and Target Cost

  • Updated cost estimate based on actual project progress,
  • Calculated by multiplying the actual unit cost by the number of completed units.
  • Significant deviations between projected and estimated costs demand remedial actions for cost control.
  • A target cost is sometimes set to bring projected costs in line.

Elements of Project Control

  • Defining project objectives, scope, budget, and schedule are essential steps.
  • Measuring progress (actual progress, time elapsed, money spent) and analyzing project performance with respect to the established baseline are core elements.
  • Implementing corrective actions to keep projects on track is critical to managing costs and timelines

Objectives of Project Control

  • Generating historical data for future estimations.
  • Establishing benchmarks to compare actual progress against estimated timelines and budgets.
  • Motivating project teams for higher performance and efficiency.
  • Clearly defining responsibilities and credit allocation.
  • Identifying methods for cost reduction.
  • Alerting the relevant management to any potential corrective actions required during the project (not just after).

Cost and Schedule Analysis

  • Performed at specific points during project execution to track progress relative to the initial estimations.
  • Projects typically begin slowly, accelerate as resources and efficiency improve, and then slow again due to closing activities.
  • Provides a quantitative assessment to ascertain project's progress compared to planned schedule and budget.

Cost Analysis

  • Evaluating actual project cost relative to the initial estimated cost.
  • Comparing completed units to the total anticipated units to ascertain percentage completion.
  • Analyzing actual spent hours against the hours estimated to evaluate if the project is running over or under budget.

Schedule Analysis

  • Assessing project progress with respect to the agreed-upon project schedule and timetable.
  • Calculate completed percentage to establish the current completion time status.
  • Calculate the difference between anticipated completion period versus the elapsed time from project start to assess delay patterns

Cost and Schedule Analysis Example

  • Example case study illustrating how to calculate cost and schedule completion status.
  • Includes calculations for completed area, man-hours spent, and efficiency rates.
  • Clearly defines the approach to identifying whether budgets are being met, and whether schedules are being met.

Earned Value Analysis

  • Essential for assessing project status comprehensively by merging cost and schedule criteria.

Earned Value Elements

  • Actual Cost of Work Performed (ACWP) records project expenditures.
  • Budgeted Cost of Work Performed (BCWP) or Earned Value (EV) predicts the budget for completed work.
  • Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the planned work expenditure.

Earned Value Calculations

  • Cost Performance Index (CPI) evaluates budget efficiency (CPI > 1: under budget; CPI < 1: over budget).
  • Schedule Performance Index (SPI) measures schedule adherence (SPI > 1: ahead of schedule; SPI < 1: behind schedule).
  • Cost Variance (CV) measures budgetary performance (CV > 0: under budget; CV < 0: over budget).
  • Schedule Variance (SV) measures the adherence to the project schedule(SV > 0: ahead of schedule; SV < 0: behind schedule).

EVMS Graphical Representation

  • Graphical representation of earned value metrics over time (Cost vs Time).
  • Visual method to observe progress of planned versus actual costs against the project plan schedule/time.

Project Performance Example

  • A hypothetical project baseline and current status.
  • Analyzing the project's performance and providing progress report.

Cost & Schedule Analysis (% Complete)

  • Calculating the percentage of the project that has been completed.
  • Assessing the project's financial performance (e.g.,. under/over budget).
  • Evaluating the project's schedule performance (e.g., ahead/behind schedule)

Forecasting EV

  • Estimating project's final cost(EAC).
  • Formula for EAC: ACWP + (BAC − BCWP).
  • BAC = Budget at Completion.

Original Budget & Schedule

  • Project schedule with milestones and cost durations.
  • Current progress status.
  • Costs incurred.

How is the Project Doing?

  • Guidelines for evaluating project performance.
  • Key indicators to evaluate the project (ACWP, BCWS, BCWP, SPI, CV, CPI, EAC)

Formalize Judgment: $

  • Calculating the cost of each unit.
  • Calculating the total cost of completed units.
  • Project's cost and schedule performance analysis.

Schedule?

  • Calculating the expected project completion timeline based on the established baseline.
  • Calculating schedule performance index (SPI).
  • Calculating schedule variance (SV).

Project Performance Results

  • Summary of project status—under budget and ahead of schedule.
  • What is expected final cost?

Project Performance Results

Additional Notes

  • The provided information includes examples of calculation methods for various metrics (e.g., costs, schedule, resources, etc.).
  • Practical application to real-world scenarios of the discussed formulas and metrics.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

More Like This

Construction Manpower Safety 1.0
21 questions
Construction Financial Planning and Cost Control
10 questions
Cost Control in Construction Quiz
18 questions
Use Quizgecko on...
Browser
Browser