Podcast
Questions and Answers
Which of the following must be included in a change order?
Which of the following must be included in a change order?
What can result from the owner issuing a suspension order?
What can result from the owner issuing a suspension order?
Which reason is NOT valid for contract termination by the owner?
Which reason is NOT valid for contract termination by the owner?
What defines liquidated damages in a construction contract?
What defines liquidated damages in a construction contract?
Signup and view all the answers
What does retainage refer to in the context of progress payments?
What does retainage refer to in the context of progress payments?
Signup and view all the answers
What is a Request for Information (RFI)?
What is a Request for Information (RFI)?
Signup and view all the answers
Which of the following may NOT contribute to construction delays?
Which of the following may NOT contribute to construction delays?
Signup and view all the answers
What does the term 'substantial completion' refer to?
What does the term 'substantial completion' refer to?
Signup and view all the answers
Which of the following delays is considered excusable?
Which of the following delays is considered excusable?
Signup and view all the answers
Under which circumstances would a contractor request a time extension?
Under which circumstances would a contractor request a time extension?
Signup and view all the answers
What is the primary purpose of the Notice to Proceed?
What is the primary purpose of the Notice to Proceed?
Signup and view all the answers
What is the role of a subcontractor in a construction project?
What is the role of a subcontractor in a construction project?
Signup and view all the answers
Which of the following is NOT a purpose of the pre-construction conference?
Which of the following is NOT a purpose of the pre-construction conference?
Signup and view all the answers
What process is involved in shop drawings approval?
What process is involved in shop drawings approval?
Signup and view all the answers
What document is issued to preserve bid prices when a project is delayed for reasons other than the owner's fault?
What document is issued to preserve bid prices when a project is delayed for reasons other than the owner's fault?
Signup and view all the answers
Who typically participates in the pre-construction conference?
Who typically participates in the pre-construction conference?
Signup and view all the answers
Which of the following tasks is NOT part of construction contract administration?
Which of the following tasks is NOT part of construction contract administration?
Signup and view all the answers
What type of information do shop drawings typically contain?
What type of information do shop drawings typically contain?
Signup and view all the answers
What must a contractor do to receive progress payments in a unit-price contract?
What must a contractor do to receive progress payments in a unit-price contract?
Signup and view all the answers
What happens to any profit saved on a job completed under a lump-sum contract?
What happens to any profit saved on a job completed under a lump-sum contract?
Signup and view all the answers
What is required from the contractor in a Cost Plus Fixed Fee (CPFF) contract?
What is required from the contractor in a Cost Plus Fixed Fee (CPFF) contract?
Signup and view all the answers
When might retainage be withheld during the payment process?
When might retainage be withheld during the payment process?
Signup and view all the answers
What must a contractor show when submitting a request for payment?
What must a contractor show when submitting a request for payment?
Signup and view all the answers
In what situation is a contractor liable for additional costs in a lump-sum contract?
In what situation is a contractor liable for additional costs in a lump-sum contract?
Signup and view all the answers
How is the total bid amount determined in a unit-price contract?
How is the total bid amount determined in a unit-price contract?
Signup and view all the answers
What distinguishes a Cost Plus Fixed Fee contract from other types?
What distinguishes a Cost Plus Fixed Fee contract from other types?
Signup and view all the answers
What indicates the official start date for a construction project?
What indicates the official start date for a construction project?
Signup and view all the answers
What is the purpose of a change order in a construction contract?
What is the purpose of a change order in a construction contract?
Signup and view all the answers
Which of the following is NOT a reason for issuing a change order?
Which of the following is NOT a reason for issuing a change order?
Signup and view all the answers
What must occur if a change in the project is needed?
What must occur if a change in the project is needed?
Signup and view all the answers
What is one consequence of a contractor remaining mobilized on site longer than planned?
What is one consequence of a contractor remaining mobilized on site longer than planned?
Signup and view all the answers
Which of these clauses is integrated with the change clause to address serious problems?
Which of these clauses is integrated with the change clause to address serious problems?
Signup and view all the answers
What does a change order typically require after the execution of a contract?
What does a change order typically require after the execution of a contract?
Signup and view all the answers
What is a potential issue that can result from contract changes?
What is a potential issue that can result from contract changes?
Signup and view all the answers
Study Notes
Construction Phase
- Notice to Proceed: Starts the contractor's right to access the owner's property after contract award.
- Letter of Intent: Issued when the project is delayed, to avoid losing bid prices.
- Pre-Construction Conference: Communication forum for the owner, designer, general contractor, specialty contractors, and municipal authorities.
- Subcontracts: Specialty contractors work under contract directly with the general contractor, not the owner.
- Construction Contract Administration (A/E) - Review submittals, shop drawings, observe construction, prepare change orders, interpret contracts, certify pay requests, and inspect work.
- Submittals/Shop Drawings: Material samples, product data, certifications, and calculations are reviewed and approved by the architect before construction.
- Shop Drawings: Contain information about products used in the project and must be approved by the owner or designer.
- Request for Information (RFI): Written communication to track questions and answers.
- Time Extensions: Delays affect project completion and can be caused by the owner, unexpected weather, or other unforeseen circumstances.
- Delays: Can be excusable (compensable or non-compensable) or non-excusable.
- Reasons for Delays: Design changes, owner-required changes, late approvals, unexpected weather, labor issues, unexpected site conditions, and material delivery delays.
- Substantial Completion Date: The date the facility is sufficiently complete for the owner to use.
- Time Provisions: The start and completion dates are defined in the contract.
- Change Clause: Mechanism for adjusting plans, specifications, and incorporating contractor suggestions.
- Change Order: A written order signed by the owner and architect to change the work, adjust the contract sum or time.
- Change Order Procedures: Owner communicates the change to the contractor, contractor responds with a price quotation, owner accepts or negotiates.
- Suspension of Work: Issued by the owner and can be costly to the contractor.
- Termination: Contract termination can occur due to owner failure to pay, court orders, or unwarranted delays.
- Liquidated Damages: Pre-determined amount payable to the owner for failing to complete the project on time.
- Progress Payment: Periodic payments to the contractor (e.g. monthly), with a percentage held back as retainage to ensure project completion.
- Basis for Payment Amount: Determined by the type of contract used (lump-sum, unit-price, or cost plus fixed fee).
Payment
- Lump-Sum Contract: Fixed price with no additional cost to the owner unless changes are approved.
- Unit-Price Contract: The contractor bids a price per unit based on the engineer's estimate and the quantity of work.
- Cost Plus Fixed Fee (CPFF): The contractor is reimbursed for actual costs plus a fixed fee for profit.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Explore key concepts and processes involved in the construction phase of a project. This quiz covers important elements such as notices to proceed, contracts, and the roles of various stakeholders. Test your knowledge on construction administration and communication in this essential phase.