Construction Phase Overview
34 Questions
1 Views

Construction Phase Overview

Created by
@HaleAnecdote

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which of the following must be included in a change order?

  • Timeline for project handover
  • Changes required under this order (correct)
  • The contractor's personal information
  • Owner's future project plans
  • What can result from the owner issuing a suspension order?

  • Stabilization of project costs
  • Increase in project funding
  • Automatic contract termination
  • Costly demobilization for the contractor (correct)
  • Which reason is NOT valid for contract termination by the owner?

  • Delays caused by weather conditions (correct)
  • Unwarranted delay by the design professional
  • Owner failure to pay promptly
  • Halting of work by court order
  • What defines liquidated damages in a construction contract?

    <p>Pre-determined damages for breach of contract</p> Signup and view all the answers

    What does retainage refer to in the context of progress payments?

    <p>A percentage of payment held back by the owner</p> Signup and view all the answers

    What is a Request for Information (RFI)?

    <p>A written communication to document questions and answers.</p> Signup and view all the answers

    Which of the following may NOT contribute to construction delays?

    <p>Advanced planning and scheduling</p> Signup and view all the answers

    What does the term 'substantial completion' refer to?

    <p>The date when the construction is usable by the owner.</p> Signup and view all the answers

    Which of the following delays is considered excusable?

    <p>Strikes affecting multiple projects.</p> Signup and view all the answers

    Under which circumstances would a contractor request a time extension?

    <p>Owner's error in design.</p> Signup and view all the answers

    What is the primary purpose of the Notice to Proceed?

    <p>To establish the contractor’s right to access the owner’s property</p> Signup and view all the answers

    What is the role of a subcontractor in a construction project?

    <p>To perform work in a specialty area and contract directly with the general contractor</p> Signup and view all the answers

    Which of the following is NOT a purpose of the pre-construction conference?

    <p>Reviewing shop drawings</p> Signup and view all the answers

    What process is involved in shop drawings approval?

    <p>Approval must come from the owner or designer before use</p> Signup and view all the answers

    What document is issued to preserve bid prices when a project is delayed for reasons other than the owner's fault?

    <p>Letter of Intent</p> Signup and view all the answers

    Who typically participates in the pre-construction conference?

    <p>Owners, designers, general contractors, and municipal authorities</p> Signup and view all the answers

    Which of the following tasks is NOT part of construction contract administration?

    <p>Negotiating with subcontractors</p> Signup and view all the answers

    What type of information do shop drawings typically contain?

    <p>Details about products to be incorporated into the project</p> Signup and view all the answers

    What must a contractor do to receive progress payments in a unit-price contract?

    <p>Submit an engineer's estimate of quantities.</p> Signup and view all the answers

    What happens to any profit saved on a job completed under a lump-sum contract?

    <p>It belongs to the contractor.</p> Signup and view all the answers

    What is required from the contractor in a Cost Plus Fixed Fee (CPFF) contract?

    <p>The contractor's costs must be regularly audited.</p> Signup and view all the answers

    When might retainage be withheld during the payment process?

    <p>When the application for payment is reviewed.</p> Signup and view all the answers

    What must a contractor show when submitting a request for payment?

    <p>Evidence that the price is correct.</p> Signup and view all the answers

    In what situation is a contractor liable for additional costs in a lump-sum contract?

    <p>If the scope of work has not changed.</p> Signup and view all the answers

    How is the total bid amount determined in a unit-price contract?

    <p>By multiplying unit prices by estimated quantities.</p> Signup and view all the answers

    What distinguishes a Cost Plus Fixed Fee contract from other types?

    <p>The contractor is reimbursed for all materials plus a fixed fee.</p> Signup and view all the answers

    What indicates the official start date for a construction project?

    <p>The date established in a notice to proceed</p> Signup and view all the answers

    What is the purpose of a change order in a construction contract?

    <p>To authorize changes in details or conditions of the work</p> Signup and view all the answers

    Which of the following is NOT a reason for issuing a change order?

    <p>Completion of the project ahead of schedule</p> Signup and view all the answers

    What must occur if a change in the project is needed?

    <p>It must be documented in writing.</p> Signup and view all the answers

    What is one consequence of a contractor remaining mobilized on site longer than planned?

    <p>Interference with planned deliveries</p> Signup and view all the answers

    Which of these clauses is integrated with the change clause to address serious problems?

    <p>Dispute clause</p> Signup and view all the answers

    What does a change order typically require after the execution of a contract?

    <p>Reapproval by the architect and contractor</p> Signup and view all the answers

    What is a potential issue that can result from contract changes?

    <p>Disruption of order sequences</p> Signup and view all the answers

    Study Notes

    Construction Phase

    • Notice to Proceed: Starts the contractor's right to access the owner's property after contract award.
    • Letter of Intent: Issued when the project is delayed, to avoid losing bid prices.
    • Pre-Construction Conference: Communication forum for the owner, designer, general contractor, specialty contractors, and municipal authorities.
    • Subcontracts: Specialty contractors work under contract directly with the general contractor, not the owner.
    • Construction Contract Administration (A/E) - Review submittals, shop drawings, observe construction, prepare change orders, interpret contracts, certify pay requests, and inspect work.
    • Submittals/Shop Drawings: Material samples, product data, certifications, and calculations are reviewed and approved by the architect before construction.
    • Shop Drawings: Contain information about products used in the project and must be approved by the owner or designer.
    • Request for Information (RFI): Written communication to track questions and answers.
    • Time Extensions: Delays affect project completion and can be caused by the owner, unexpected weather, or other unforeseen circumstances.
    • Delays: Can be excusable (compensable or non-compensable) or non-excusable.
    • Reasons for Delays: Design changes, owner-required changes, late approvals, unexpected weather, labor issues, unexpected site conditions, and material delivery delays.
    • Substantial Completion Date: The date the facility is sufficiently complete for the owner to use.
    • Time Provisions: The start and completion dates are defined in the contract.
    • Change Clause: Mechanism for adjusting plans, specifications, and incorporating contractor suggestions.
    • Change Order: A written order signed by the owner and architect to change the work, adjust the contract sum or time.
    • Change Order Procedures: Owner communicates the change to the contractor, contractor responds with a price quotation, owner accepts or negotiates.
    • Suspension of Work: Issued by the owner and can be costly to the contractor.
    • Termination: Contract termination can occur due to owner failure to pay, court orders, or unwarranted delays.
    • Liquidated Damages: Pre-determined amount payable to the owner for failing to complete the project on time.
    • Progress Payment: Periodic payments to the contractor (e.g. monthly), with a percentage held back as retainage to ensure project completion.
    • Basis for Payment Amount: Determined by the type of contract used (lump-sum, unit-price, or cost plus fixed fee).

    Payment

    • Lump-Sum Contract: Fixed price with no additional cost to the owner unless changes are approved.
    • Unit-Price Contract: The contractor bids a price per unit based on the engineer's estimate and the quantity of work.
    • Cost Plus Fixed Fee (CPFF): The contractor is reimbursed for actual costs plus a fixed fee for profit.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Explore key concepts and processes involved in the construction phase of a project. This quiz covers important elements such as notices to proceed, contracts, and the roles of various stakeholders. Test your knowledge on construction administration and communication in this essential phase.

    More Like This

    Mastering Contract Administration
    26 questions
    Contract Administration Essentials
    52 questions
    CE24: Construction Phase Services Quiz
    10 questions
    Construction Management Principles
    40 questions
    Use Quizgecko on...
    Browser
    Browser