Podcast
Questions and Answers
What percentage range do materials typically constitute of overall project costs in construction?
What percentage range do materials typically constitute of overall project costs in construction?
- 10% to 20%
- 20% to 30%
- 40% to 60% (correct)
- 70% to 80%
Which of the following is a potential consequence of poor materials management on a construction project?
Which of the following is a potential consequence of poor materials management on a construction project?
- Lower labor costs
- Large and avoidable costs (correct)
- Reduced project duration
- Improved quality control
What risk is associated with purchasing materials too early in a construction project?
What risk is associated with purchasing materials too early in a construction project?
- Decreased risk of theft
- Lower transportation costs
- Capital being tied up and interest charges incurred (correct)
- Reduced supplier discounts
Which of the following is a risk associated with purchasing materials too late in a construction project?
Which of the following is a risk associated with purchasing materials too late in a construction project?
What does the definition of material management emphasize to ensure the quality and quantity of materials?
What does the definition of material management emphasize to ensure the quality and quantity of materials?
What are the '5 Rs of Materials Management' primarily focused on?
What are the '5 Rs of Materials Management' primarily focused on?
What is the core principle of the Just-in-time theory in materials management?
What is the core principle of the Just-in-time theory in materials management?
What is the main idea behind the inventory buffer theory?
What is the main idea behind the inventory buffer theory?
Which of the following is considered a type of construction material?
Which of the following is considered a type of construction material?
How does the delivery process differ among the three types of construction materials?
How does the delivery process differ among the three types of construction materials?
Which of the following materials is classified as a bulk material?
Which of the following materials is classified as a bulk material?
How are some bulk materials like earthwork or gravels measured?
How are some bulk materials like earthwork or gravels measured?
Which of the following materials is considered a 'standard off-the-shelf material'?
Which of the following materials is considered a 'standard off-the-shelf material'?
Which characteristic defines 'standard off-the-shelf materials'?
Which characteristic defines 'standard off-the-shelf materials'?
Which of the following is an example of a 'fabricated material'?
Which of the following is an example of a 'fabricated material'?
What distinguishes fabricated materials from other types of construction materials?
What distinguishes fabricated materials from other types of construction materials?
In the steps of material management, which process comes directly after 'Request for Quotation (RFQ)'?
In the steps of material management, which process comes directly after 'Request for Quotation (RFQ)'?
What is the main purpose of 'Tracking & Expediting' in material management?
What is the main purpose of 'Tracking & Expediting' in material management?
Which of the following is a major category of costs associated with construction materials?
Which of the following is a major category of costs associated with construction materials?
What do 'purchase costs' in material management include?
What do 'purchase costs' in material management include?
What is a benefit of bulk purchases in construction materials?
What is a benefit of bulk purchases in construction materials?
Which of the following reflects the administrative expense of issuing a purchase order to an outside supplier?
Which of the following reflects the administrative expense of issuing a purchase order to an outside supplier?
What do order costs include?
What do order costs include?
What is included in 'holding costs' in material management?
What is included in 'holding costs' in material management?
Holding costs typically represent what percentage range of the average inventory value over a year?
Holding costs typically represent what percentage range of the average inventory value over a year?
What does 'obsolescence' refer to within the context of holding costs?
What does 'obsolescence' refer to within the context of holding costs?
What are 'unavailability costs' also known as?
What are 'unavailability costs' also known as?
Which of the following situations leads to 'unavailability costs'?
Which of the following situations leads to 'unavailability costs'?
What does 'lead time' refer to in ordering materials?
What does 'lead time' refer to in ordering materials?
What factors does the 'lead time' period depend on?
What factors does the 'lead time' period depend on?
What is a consequence of providing a long lead time in ordering materials?
What is a consequence of providing a long lead time in ordering materials?
How should a project manager determine how much lead time to provide for ordering an item?
How should a project manager determine how much lead time to provide for ordering an item?
What tradeoff does the lead time primarily depend on?
What tradeoff does the lead time primarily depend on?
If $E(T)$ represents the expected delivery time and $D$ represents additional days required, how is lead time (L) calculated?
If $E(T)$ represents the expected delivery time and $D$ represents additional days required, how is lead time (L) calculated?
Flashcards
Materials in Construction
Materials in Construction
Materials are a major class of construction resources, typically constituting 40-60% of project costs.
Material Management
Material Management
An integrated process for planning and controlling efforts to ensure the quality and quantity of materials are specified, obtained, and available at a reasonable cost and when needed.
5 Rs of Materials Management
5 Rs of Materials Management
Acquisition of materials and services of the right quality, in the right quantity, at the right time, from the right source, and at the right price.
Just-in-time Theory
Just-in-time Theory
Signup and view all the flashcards
Inventory Buffer Theory
Inventory Buffer Theory
Signup and view all the flashcards
Bulk Materials
Bulk Materials
Signup and view all the flashcards
Standard Off-the-Shelf Materials
Standard Off-the-Shelf Materials
Signup and view all the flashcards
Fabricated Materials
Fabricated Materials
Signup and view all the flashcards
Purchase Costs
Purchase Costs
Signup and view all the flashcards
Order Costs
Order Costs
Signup and view all the flashcards
Holding Costs
Holding Costs
Signup and view all the flashcards
Examples of Holding Costs
Examples of Holding Costs
Signup and view all the flashcards
Unavailability Costs
Unavailability Costs
Signup and view all the flashcards
Lead Time (L)
Lead Time (L)
Signup and view all the flashcards
Components of Lead Time
Components of Lead Time
Signup and view all the flashcards
Lead Time Tradeoff
Lead Time Tradeoff
Signup and view all the flashcards
Lead Time Calculation
Lead Time Calculation
Signup and view all the flashcards
Study Notes
- Materials are a major construction resource, representing 40-60% of project costs.
- Poor material management results in large, avoidable costs, and issues such as wrong materials, large inventories, damage, and shortages.
Introduction to Material Management
- Purchasing materials early can tie up capital and incur interest, risk deterioration or theft, and require special storage for items like electrical equipment.
- Purchasing materials late can result in delays and extra expenses.
- Material management involves planning and controlling efforts to ensure the right quality and quantity of materials are specified, obtained at a reasonable cost, and available on time.
- Objectives of material management, also called the "5 Rs", include acquiring materials and services of the right quality, quantity, time, source, and price.
- The Just-in-time theory focuses on delivering materials only when needed for installation, avoiding on-site storage.
- The Inventory buffer theory prioritizes purchasing, delivering, and storing all materials on-site before installation.
- Construction materials are classified into bulk materials, standard off-the-shelf materials, and fabricated members or units.
- Delivery processes, transportation, field storage and installation differ for each material class.
- Equipment needed to handle and haul materials varies by material class.
Bulk Materials
- Bulk materials are in their natural or semi-processed state, such as sand, cement, and ready-mix concrete.
- These materials are commonly found in large quantities on construction sites.
- Earthwork or gravels are examples of materials measured in bank (solid in situ) volume.
- Quantities for delivery differ based on the volume measures and characteristics of the materials.
- Examples of typical bulk materials include paving materials, fill materials, dampproofing membrane, lumber, form materials, ready-mix concrete, wire mesh, reinforcing steel, masonry, soils, piping, electrical conduit, and caulking.
Standard off-the-Shelf Materials
- These are processed materials with standard dimensions and specifications.
- Examples include valves, standard pipes, bathroom fixtures, and AC units.
- They're easily stockpiled, and the delivery process is simple.
- Mechanical and Plumbing Equipment and Materials are: Fire protection equipment, Water supply equipment, Valves, Drains, Clean-outs, Plumbing fixtures, Gas-piping accessories, Pumps, Boilers, Cooling towers, Control systems, Air-handling equipment and Refrigeration units (chillers)
Fabricated Materials
- These are custom-built to specific dimensions and specifications for projects.
- Steel connections, steel tanks, and welded or bolted connections are examples.
- Units are partly or fully fabricated in a shop and then shipped.
- Examples of fabricated materials include: Precast panels and decks, Stone veneers, Miscellaneous and special formed metals, Ornamental metals, Millwork, Custom casework and cabinetwork, Sheet metal work, Sheet metal veneers, Hollow metal doors and frames, Wood and plastic laminate doors, Glass and glazing, Storefront and Window walls and curtain walls.
Steps of Material Management
- Request for quotation (RFQ) --> Bidding & vendor selection --> Purchase order (PO) --> Tracking & Expediting --> Transportation & delivery --> Receiving and inspection --> Inventory --> Use.
Elements of Material Costs
- Major cost categories associated with construction materials are: purchase costs, order costs, holding costs, and unavailability costs.
Purchase Costs
- The price paid to the vendor includes transportation.
- Discounts are common for bulk purchases in construction, lowering unit cost as quantity increases.
- Bulk purchases ensure material homogeneity, which is desirable when items like bricks need consistent color or size.
- Large quantity purchases can lead to high holding costs.
Order Costs
- Reflect the administrative expense of issuing a purchase order to an outside supplier.
- Order costs cover making requisitions, analyzing vendors, writing purchase orders, receiving and inspecting materials, checking orders, and record maintenance.
- Order costs are a small portion of total material management costs but can require substantial time.
Holding Costs
- Costs associated with keeping materials unused, including capital costs, handling, storage, obsolescence, shrinkage, and deterioration.
- Many holding cost components are hard to predict, especially for high-tech items.
- Holding costs typically represent 20 to 40% of the average inventory value annually.
- Average material inventory on a project is $1 million, holding cost might be $200,000 to $400,000.
- Capital costs are results from the opportunity cost or financial expense of capital tied up in inventory.
- Handling and storage represent the movement and protection charges incurred for materials.
- Storage costs include disruption caused to other project activities by large inventories of materials that get in the way
- Obsolescence is the risk that an item will lose value because of changes in specifications.
- Shrinkage is the decrease in inventory over time due to theft or loss.
- Deterioration reflects a change in material quality due to age or environmental degradation.
Unavailability Costs
- Occurs when materials are not available on the job site by the desired time.
- Also known as stockout or depletion cost.
- Shortages may delay work, leading to wasted resources or project delays.
- The cost associated with a shortage is hard to assess.
- The material used for one activity can be assigned for another depending on which activities are critical potentially avoiding delays.
Lead time (L)
- The time period ahead of the delivery date at which a PO should be sent to the vendor
- Depends on processing time (R) and shipping time (S), where T=R+S (uncertain)
- The project manager must decide how much lead time to provide in ordering the item
- Ordering early increases availability but also increases inventory costs and the chance of spoilage on site
- Assume T as a random variable with probability p(t) for delivery on day t.
- The probability of delivery on or before day t is p(T ≤ t) = Σ p(u) for u=0 to t.
- Expected delivery time is E(T) = Σ t(p(t)) for t=a to b, "a" and "b" are the lower and upper bounds of possible delivery dates.
- Lead time depends on the tradeoff between holding costs and unavailability costs.
- Then, lead time (L) is calculated as follows L = E(T) + D where,
- D may vary from 0 to the number of additional days required to produce certain delivery on the desired date.
Illustrative Example 1
-
Calculate the expected time of delivery.
-
Determine the appropriate lead time to ensure
- No unavailability cost is paid.
- No holding cost is paid.
-
Determine the appropriate lead time to ensure that there is at least a 90% probability that material will not arrive late for use.
Illustrative Example 2
- This example involves using probability, holding costs, and unavailability costs to determine when to order materials to minimize costs, considering variables such as liquidated damages and potential project delays.
- In summary, the most suitable time to order the material is on day 50 after weighing all holding and unavailability costs at various delivery dates.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.