Construction Management Quiz
40 Questions
2 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which of the following is not considered a Variation Order?

  • Extra work order
  • Resume order (correct)
  • Change order
  • Supplemental agreement
  • A project may be granted a time extension for delays due to reasons beyond the contractor's control if the affected works are what type of activities?

  • Critical activities (correct)
  • Dummy activities
  • Hammock activities
  • Non-critical activities
  • If work is 50% completed satisfactorily, what should be the retention rate on progress payments?

  • 15%
  • 5%
  • 20%
  • 10% (correct)
  • What is the permitted variation from the design thickness of a layer of aggregate base course?

    <p>± 20 mm</p> Signup and view all the answers

    What is the permitted variation from the design thickness of a layer of aggregate subbase course?

    <p>± 30 mm</p> Signup and view all the answers

    What is the rate of application of seal coat using cutback asphalt?

    <p>1.5-3.0 li./sq.m.</p> Signup and view all the answers

    What is the required area of the trial section to assess material suitability for construction?

    <p>About 500 sq.m.</p> Signup and view all the answers

    What is the accepted proportion mixture of cement for a Portland cement stabilized road mix?

    <p>5 to 12 mass percent</p> Signup and view all the answers

    Defective works in a project should be reported to the contractor through which method?

    <p>Inspection report</p> Signup and view all the answers

    How much percentage is typically withheld on general items until final acceptance of a project?

    <p>20%</p> Signup and view all the answers

    What is the accepted proportion mixture of lime for a Lime stabilized road mix?

    <p>4 to 15 mass percent</p> Signup and view all the answers

    Which of the following is not considered a construction safety procedure?

    <p>Sending workers engaged in clearing without protection</p> Signup and view all the answers

    Which of the following is not a cause of delay in project implementation?

    <p>Pre-determined rainy month in the area</p> Signup and view all the answers

    The bar chart used in project management is commonly referred to as what?

    <p>Gantt chart</p> Signup and view all the answers

    After 50% completion of work, what is the retention rate imposed if the work is satisfactory?

    <p>10%</p> Signup and view all the answers

    Which type of activities, as shown in the PERT/CPM diagram, may grant a time extension due to delays beyond the contractor's control?

    <p>Critical activities</p> Signup and view all the answers

    If the required thickness of item 200 is 300 mm, the material may be spread and compacted in how many layers?

    <p>Two</p> Signup and view all the answers

    What is the term for a record compiled to contain the data and history of a project?

    <p>Log book</p> Signup and view all the answers

    In riprapping construction, which element is provided as a water outlet and lateral pressure reliever?

    <p>Weep hole</p> Signup and view all the answers

    What do you call the process of strengthening an existing pavement by adding thickness?

    <p>Overlaying</p> Signup and view all the answers

    Concrete mix should not be in place for more than how many minutes from when the ingredients were mixed?

    <p>45</p> Signup and view all the answers

    The maximum time allowed from when water is added to concrete mix until it is placed is?

    <p>45 mins</p> Signup and view all the answers

    Before placing concrete, the base of a roadway should be kept moist for at least how long?

    <p>3 hrs</p> Signup and view all the answers

    To protect newly poured Portland cement concrete from rain, which material is NOT required?

    <p>Plastic water stops</p> Signup and view all the answers

    What is the allowable minimum penetration of piles in firm material?

    <p>4.0 m</p> Signup and view all the answers

    What should the condition of the tack coat be before the next course is applied?

    <p>Sticky</p> Signup and view all the answers

    Concrete mix not placed within ______________ minutes from the time ingredients were charged should not be used.

    <p>90</p> Signup and view all the answers

    What is the minimum allowable atmospheric temperature in the application of Item 305 bituminous material?

    <p>5 ºC</p> Signup and view all the answers

    Why must the inside face of a pothole be made vertical before patching using asphalt?

    <p>To ensure bond between the new mix and old surface</p> Signup and view all the answers

    Repainting of a steel bridge is classified as which type of maintenance activity?

    <p>Periodic maintenance</p> Signup and view all the answers

    What is the process of cutting the branches around a tree on the roadside to encourage straight growth called?

    <p>Pruning</p> Signup and view all the answers

    What is the minimum required penetration depth for piles in firm material?

    <p>75 mm</p> Signup and view all the answers

    What is a contractor entitled to claim if a project is started more than 8 months after the bidding?

    <p>Price adjustment</p> Signup and view all the answers

    Before issuing a certificate of final inspection, which conference should be conducted in the field after a project completion?

    <p>Exit conference</p> Signup and view all the answers

    In an inspection report, what is the most critical item to include aside from findings?

    <p>Recommendation of possible actions to be undertaken</p> Signup and view all the answers

    Which of the following data is not typically contained in a logbook?

    <p>Survey data</p> Signup and view all the answers

    What formula is commonly used for computing price escalation?

    <p>Economic formula</p> Signup and view all the answers

    Which date serves as the basis for computing contract price escalation in a project awarded through public bidding?

    <p>Date of bidding</p> Signup and view all the answers

    When computing contract price escalation for a project awarded through simplified bidding, which date is used?

    <p>Date of bidding</p> Signup and view all the answers

    Which of the following is not considered a flood damage mitigation measure?

    <p>Highway drainage</p> Signup and view all the answers

    Study Notes

    Variation Orders and Extensions

    • Variation Orders include change orders, extra work orders, and supplemental agreements; resume orders are not included.
    • A project may receive a time extension if delays stem from reasons beyond the contractor's control, affecting critical activities.

    Retention and Payments

    • Upon satisfactory progress at 50% completion, no extra retention is imposed; a typical retention rate is 5%.
    • General items payment typically withhold up to 20% until final project acceptance.

    Material Specifications and Quality Control

    • Permitted variation for aggregate base course thickness is ± 20 mm; subbase course thickness variation is ± 10 mm.
    • Trial section area needed for material and method testing is about 400 sq.m.

    Mixture Proportions

    • The acceptable cement mix for Portland cement stabilized road mixes is 4 to 20 mass percent.
    • Lime stabilization for road mixes accepts a lime proportion of 2 to 10 mass percent.

    Soil and Base Conditions

    • Sub-grade soil must be well compacted at optimum moisture and maximum dry density for quality control.
    • Concrete procedures dictate base moistening for at least 6 hours before placing concrete.

    Project Management and Reporting

    • Defective works are reported to the contractor through an inspection report.
    • The logbook does not include survey data but documents daily activities, weather conditions, and material usage.

    Construction Safety and Delays

    • Construction safety procedures involve proper shoring of excavations and guarding openings; logging by equipment operators is essential.
    • Causes of delays include plan revisions and inadequacies in contractor resources; natural factors like predetermined rainy seasons do not count.

    Planning Tools and Maintenance

    • Bar charts are synonymous with Gantt charts, vital for project scheduling.
    • Repainting of a steel bridge is categorized as periodic maintenance.

    Concrete Handling Regulations

    • Concrete must be mixed and placed within 90 minutes of initial mixing; transport time from addition of water to placement should not exceed 30 minutes.
    • Waterproofing materials for fresh concrete include burlap or plastic sheeting, while metal forms may not be suitable.

    Piles, Tack and Temperature Considerations

    • Minimum penetration for piles in firm material is 4.0 meters; tack coat conditions should be sticky before applying the next course.
    • The minimum temperature for bituminous material application is 10 ºC.

    Inspections, Reports, and Allowances

    • Post-final inspection, certificates of completion are contingent on conducting an exit conference.
    • Essential items in inspection reports include recommendations for actions rather than team member details.

    Price Adjustment and Flood Mitigation

    • Contract price escalation is generally computed from the effectivity date of the contract.
    • Flood damage mitigation strategies encompass reservoir flow reduction and floodplain management, while highway drainage does not qualify as a mitigation measure.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    Test your knowledge on construction management concepts and the handling of variation orders. This quiz covers topics such as cost increases in materials, time extensions due to delays, and types of orders in project management. Perfect for students and professionals in the field of construction management.

    More Like This

    Construction Management
    26 questions

    Construction Management

    WorthwhilePyrite5473 avatar
    WorthwhilePyrite5473
    Construction Management M-1.1
    10 questions
    Construction Management Module 1
    38 questions
    Use Quizgecko on...
    Browser
    Browser