Podcast
Questions and Answers
Under which condition is a change order not required?
Under which condition is a change order not required?
- Decrease in work due to deletion of work items (correct)
- Increase in cost due to construction materials
- Reclassification of items of works
- Aggregate cost increase limited to 25% of original cost
Which of the following is not classified as a Variation Order?
Which of the following is not classified as a Variation Order?
- Extra work order (correct)
- Change order
- Supplemental agreement
- Resume order
What is the retention rate imposed if work is 50% complete and satisfactory?
What is the retention rate imposed if work is 50% complete and satisfactory?
- 5%
- 20%
- 10% (correct)
- 15%
What is the permitted variation from the design thickness for an aggregate subbase course?
What is the permitted variation from the design thickness for an aggregate subbase course?
What is the minimum cement content per cubic meter of class B concrete when one bag weighs 40 kg?
What is the minimum cement content per cubic meter of class B concrete when one bag weighs 40 kg?
What is the minimum area required for the trial section to evaluate material suitability and construction method efficiency?
What is the minimum area required for the trial section to evaluate material suitability and construction method efficiency?
How often can a contractor request progress payment?
How often can a contractor request progress payment?
Before asphalt pavement is laid on a granular base, what type of liquid asphalt is typically applied?
Before asphalt pavement is laid on a granular base, what type of liquid asphalt is typically applied?
Which test is primarily used to differentiate clay from silt?
Which test is primarily used to differentiate clay from silt?
What is the effective sieve no. on which the Atterberg limit tests are performed?
What is the effective sieve no. on which the Atterberg limit tests are performed?
Flashcards
Change order conditions
Change order conditions
Change orders cannot be issued if the aggregate cost increase exceeds 25% of the original cost, or if there's a decrease in work due to deleting work items.
Variation Order Exclusion
Variation Order Exclusion
A supplemental agreement is not considered a variation order; while change orders and extra work orders are.
Time extension eligibility
Time extension eligibility
A project delay due to uncontrollable factors might allow a time extension if critical activities, as shown in PERT/CPM, are affected.
Retention rate for progress payment
Retention rate for progress payment
Signup and view all the flashcards
Aggregate base course thickness variation
Aggregate base course thickness variation
Signup and view all the flashcards
Minimum cement for class B concrete
Minimum cement for class B concrete
Signup and view all the flashcards
Concrete cylinder testing volume
Concrete cylinder testing volume
Signup and view all the flashcards
Distinguishing clay from silt
Distinguishing clay from silt
Signup and view all the flashcards
Atterberg limit sieve size
Atterberg limit sieve size
Signup and view all the flashcards
Progress payment frequency
Progress payment frequency
Signup and view all the flashcards
Study Notes
DPWH Accreditation of Contractors'/Consultants' Project Engineer Reviewer Quiz App
- This is a quiz app for DPWH contractors/consultants' project engineer reviewers.
- It is a February 2023 edition.
- Developed by Engr. Jestoni G. Elano, CE, ME II, SO2.
PE Exam Reference E-Books
- DGCS Vol. I to 6
- Accessibility Law (BP 344)
- Simplified Construction Handbook
- Blue Book Vol. II, 2013
- Blue Book Vol. III, 1995
- Building Cons. Methodology
- Road Cons. Methodology
- Bridge Cons. Methodology
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your knowledge on key concepts in construction management. This quiz covers topics such as change orders, retention rates, material suitability, and testing methods. Answer questions to assess your understanding of essential principles in the field.