Podcast
Questions and Answers
Which of the following reflects the primary aim of construction cost engineering?
Which of the following reflects the primary aim of construction cost engineering?
- To deliver projects on time and within budget through effective cost management. (correct)
- To only focus on minimizing initial cost estimations.
- To extend project timelines to accommodate budget changes.
- To maximize the use of expensive materials to ensure quality.
A construction project forecasts profits amounting to 8% to 10% of the estimated direct cost (EDC). Which type of project is likely being undertaken?
A construction project forecasts profits amounting to 8% to 10% of the estimated direct cost (EDC). Which type of project is likely being undertaken?
- A horizontal project
- A vertical project worth P5 million or less (correct)
- A preliminary project
- A vertical project worth over P5 million
What is the main goal of 'Value Engineering' in construction cost management?
What is the main goal of 'Value Engineering' in construction cost management?
- Increasing project costs to ensure higher quality materials are used.
- Using the cheapest materials available regardless of their impact on quality.
- Optimizing project design and material selection to reduce costs without sacrificing quality. (correct)
- Ignoring cost overruns to maintain the original project timeline.
What is the main purpose of implementing cost-saving strategies during project execution?
What is the main purpose of implementing cost-saving strategies during project execution?
In which stage of the construction project lifecycle is the project's blueprint developed by architects, engineers, and planners?
In which stage of the construction project lifecycle is the project's blueprint developed by architects, engineers, and planners?
What is the primary reason Detailed Cost Estimation is performed after Preliminary Cost Estimation?
What is the primary reason Detailed Cost Estimation is performed after Preliminary Cost Estimation?
Which method involves costing out materials and labor at local rates after measuring the quantities needed for a project?
Which method involves costing out materials and labor at local rates after measuring the quantities needed for a project?
When estimating material costs, why is it typical to order 5%-10% more than the initially calculated quantity?
When estimating material costs, why is it typical to order 5%-10% more than the initially calculated quantity?
A project team is uncertain about the exact type of flooring to install but needs to include its cost in the project budget. What type of allowance should they apply?
A project team is uncertain about the exact type of flooring to install but needs to include its cost in the project budget. What type of allowance should they apply?
Which strategy is most effective for mitigating the risk of fluctuating material prices in construction projects?
Which strategy is most effective for mitigating the risk of fluctuating material prices in construction projects?
Flashcards
Construction Cost Engineering
Construction Cost Engineering
Estimating, controlling, managing, and optimizing costs in construction projects throughout its financial lifecycle to deliver the project on time and within budget.
Cost Estimation
Cost Estimation
Forecasting the costs associated with a construction project.
Cost Control
Cost Control
Ensuring actual costs align with the estimated budget and making adjustments as necessary.
Project Budgeting
Project Budgeting
Signup and view all the flashcards
Value Engineering
Value Engineering
Signup and view all the flashcards
Preliminary Estimates
Preliminary Estimates
Signup and view all the flashcards
Detailed Estimates
Detailed Estimates
Signup and view all the flashcards
Direct Costs
Direct Costs
Signup and view all the flashcards
Indirect Costs
Indirect Costs
Signup and view all the flashcards
Fixed Costs
Fixed Costs
Signup and view all the flashcards
Study Notes
- Construction cost engineering encompasses cost estimation, control, management, and optimization in construction projects.
- Aims to deliver projects on time and within budget.
Key Components of Construction Cost Engineering
- Cost estimation is the process of forecasting costs for a construction project.
- Cost control aligns real costs with the estimated budget, making necessary adjustments.
- Project budgeting sets a financial plan, forecasting resources and costs.
- Profit margins for horizontal projects are 30% of the project cost.
- Profit margins for vertical projects range from 5% to 15% of the project cost.
- Value engineering optimizes project design and materials to reduce costs without compromising quality.
Importance of Cost Engineering
- Financial management helps keep projects within budget, preventing cost overruns.
- Resource allocation uses labor, materials, and machinery efficiently to maximize productivity and minimize waste.
- Schedule control involves accurate cost estimation to plan and schedule tasks effectively, avoiding delays from unexpected costs.
- Risk management identifies cost-related risks early and mitigates them through contingency planning.
- Real-world applications in large-scale infrastructure projects address issues like fluctuating material prices and weather delays.
Roles and Responsibilities of a Cost Engineer
- Cost estimation involves developing preliminary and detailed cost estimates using historical data, industry standards, and project specifics.
- Budget management includes preparing cost breakdown structures (CBS) and budgets.
- Budget management includes tracking expenses and comparing actual costs to estimates to identify variances.
- Cost control monitors project expenditures, manages cash flow, and prevents cost overruns.
- Cost control involves implementing cost-saving strategies during project execution.
- Risk management identifies potential financial risks, such as price fluctuations and project delays.
- Risk management implements strategies like contingency allowances to address risks.
- Reporting and communication provides regular reports to stakeholders on cost performance.
- Reporting and communication advises on necessary adjustments to stay within budget.
Skills Required
- Analytical skills are required for cost breakdown and forecasting.
- Strong knowledge of construction processes and materials is important.
- Familiarity with cost estimation software like ProEst, Buildertrend, and PlanSwift is needed.
Stages of the Cost Estimation Process
- Preliminary estimates (feasibility study) provide initial figures based on available project information, using historical data or conceptual drawings.
- Detailed estimates are precise, based on detailed designs, drawings, and specifications.
- Detailed estimates include quantities of materials, labor hours, equipment costs, and overheads.
- Bid estimates (tender process) are final, competitive estimates submitted for project bids.
- Bid estimates include exact costs plus a markup for profit and risk contingency.
- Post-project evaluation compares actual costs to initial estimates.
- Post-project evaluation analyzes variances and identifies areas for improvement in future projects.
Techniques Used in Estimation
- Analogous estimating uses historical data from similar projects as a reference.
- Parametric estimating applies statistical relationships between historical data and project variables.
- Bottom-up estimating estimates costs for each individual work package and sums them.
Types of Construction Costs
- Direct costs are directly linked to construction activities.
- Labor costs consists of wages for construction workers, subcontractors, and engineers.
- Material costs consists of items like concrete, steel, bricks, and plumbing fixtures.
- Equipment costs consists of rental or purchase of machinery, such as cranes and mixers.
- Indirect costs support the project but are not directly involved in construction work.
- Overhead costs consist of office space, utilities, and administrative support (7-11% of EDC).
- Supervision costs consist of project management and supervisory staff.
- Insurance and taxes consists of ensuring the project and compliance with regulations.
- Fixed costs remain constant regardless of project size or scope.
- Site office expenses consists of renting office space and equipment.
- Project manager salary is fixed for the project duration.
- Variable costs change based on project scale and duration.
- Material costs' prices change with the amount of materials used.
- Labor costs depend on the hours worked or the number of workers employed.
Overhead Expenses
- Overhead expenses range from 7-11% of the EDC and include items like engineering and administrative supervision, transportation allowances, and office expenses.
- OCM and profit cannot be applied to items such as mobilization/demobilization, provision of service vehicle, and permits/clearances.
Construction Project Lifecycle
- The construction project lifecycle is a framework outlining the stages of a project from start to finish.
- Cost engineers ensure financial resources are allocated effectively and costs are kept under control, estimating, managing, and controlling costs throughout the project lifecycle.
Construction Phases
- The design phase involves developing the concept and plans for the project with architects, engineers, and planners.
- The design phase includes obtaining necessary permits.
- The planning phase includes detailing how project will be executed, including timelines, resources, and a detailed budget.
- During the construction phase, the construction team follows plans, managing on-site work, labor, and materials.
- The operation phase involves the handover of the building with ongoing maintenance, repairs, and operational activities.
Cost Management through the Project Lifecycle
- Budget estimates are created based on project scope and initial design plans
- Cost management focuses on value engineering to minimize costs without compromising quality.
- In the planning phase, detailed cost breakdowns are created for materials, labor, and equipment.
- In the planning phase, contingency planning for potential risks and cost overruns is considered.
- During the construction phase, there is ongoing cost tracking to monitor project expenses and prevent budget overruns.
- The construction phase involves adjustments made for changes in scope or unexpected delays.
- The operation phase includes post-construction costs, such as facility maintenance, upgrades, and repairs.
Cost Estimation Process
- Cost Estimation is a forecast of project costs based on data, scope, and objectives.
- Its a dynamic process that requires careful planning to ensure financial success.
- Prevents budget overruns
- Accurate Cost Estimation is essential for project planning and decision-making
Types of Cost Estimation
Preliminary Cost Estimation
- Provides an early cost assessment with limited project information Provides a general sense of the project’s expected costs
- Used often during the conceptual stage to determine a project’s feasibility
Detailed Cost Estimation
- Provides a specific and precise estimate using exact project details
- Usually conducted following the development of project specifications
- Results in more accurate project estimates
Methods in Cost Estimation
Unit Rate Method
- Estimates project costs based on known cost per unit metrics (e.g., cost per square meter)
- Uses the formula: Total Cost=Unit Rate×Quantity of Units
- Commonly used and very well-known
Quantity Survey Method
- Determines total costs based on the quantities of materials and labor
Steps
- Measures the quantities based on the drawing plans
- Applies local pricing for the quantities
- Accounts for the costs of equipment, and labour separately
Detailed Take-Off
- Very thorough assessment that measures all project components meticulously for an accurate cost estimate
Parametric Estimating
- Uses historic project data in order to estimate potential costs based on parameters
- Formula: Cost = Parameter x Quantity
Analogy-Based Estimating
- Compares potential project with similar ones in order to best derive an estimate
- Useful when historical data is available
Factors that Affect Cost Estimation
- Labor prices
- Material prices, particularly if newly required
- Required equipment
Estimating Material Costs
- Types of material in construction include Raw Materials, Finished Materials, and Specialty Materials
- Factors in material costs include quantity estimates, material delivery costs, and material waste.
- It is normal to order 5 - 10% more building supplies to account for breakage or defects.
Estimating Labor Costs
- Direct labor costs, such as technicians, goes to the overall cost.
- Indirect labor costs, such as employee payment, goes to the overall cost.
- Estimating labor hours is based on the complexity and individual tasks.
- Task-based estimates, workforce efficiency, and crew staffing, are all also factors.
Contingency Allowance
- Contingencies protect against price increase issues and risk.
- A risk assessment plan is useful to find contingency percentages.
Challenges in Material and Labor Costing
- Prices may fluctuate due to unexpected supply change issues, or global market trends.
- Lack of materials may drive up costs.
- Weather or difficult site conditions may also lead to increased costs.
- Use long-term supply chain agreements, or monitor potential markets to find out true cost proactively.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.