Questions and Answers

Which FIDIC form(s) specifically refer to Clause 20 for the Contractor Claim Event 'Delay in necessary drawing or instruction'?

  • SB and EB
  • YB and SB
  • RB
  • RB and EB (correct)
  • Which FIDIC form(s) entitle the Contractor to EOT (Extension of Time) and same Cost Plus Profit for the event 'Unforeseeable physical conditions at Site'?

  • RB and EB (correct)
  • YB
  • SB and EB
  • SB
  • Which FIDIC form(s) do not provide the Contractor with the right to EOT and same Cost Plus Profit for the event 'Delay in tests due to Employer'?

  • SB
  • RB (correct)
  • EB
  • YB
  • Which FIDIC form(s) entitle the Contractor to EOT and same Cost Plus Profit for the event 'Remedial work prior to Taking-Over due to Employer'?

    <p>RB and YB</p> Signup and view all the answers

    Which clause in the construction contract covers shortages in personnel or goods due to epidemic or government action?

    <p>Shortages in personnel or goods due to epidemic or government action</p> Signup and view all the answers

    What does the construction contract clause related to suspension instructed by the employer cover?

    <p>Suspension instructed by the employer</p> Signup and view all the answers

    Which type of contract is compared in terms of total claim events in the construction contract summary?

    <p>Emerald</p> Signup and view all the answers

    What does the construction contract clause related to contractor's failure to provide assistance or comply with permits address?

    <p>Contractor's failure to provide assistance or comply with permits</p> Signup and view all the answers

    Which clause in the construction contract pertains to measures to overcome slow progress?

    <p>Measures to overcome slow progress</p> Signup and view all the answers

    What is covered in the construction contract clause related to the inability to use a section of the works due to a defect?

    <p>Inability to use a section of the works due to a defect</p> Signup and view all the answers

    What does the construction contract clause related to the comparison of claim events across different types of contracts emphasize?

    <p>Comparison of claim events</p> Signup and view all the answers

    Which aspect is detailed in the construction contract clause related to resources used in executing a variation?

    <p>Resources used in executing a variation</p> Signup and view all the answers

    What does the construction contract clause related to EOT/adjustments to contract price due to variation by engineer instruction cover?

    <p>EOT/adjustments to contract price due to variation by engineer instruction</p> Signup and view all the answers

    What is the focus of the construction contract clause related to the revision of schedule of payments not based on progress?

    <p>Revision of schedule of payments not based on progress</p> Signup and view all the answers

    What does the construction contract clause related to the entitlements in the construction contract summary emphasize?

    <p>Entitlements in the construction contract</p> Signup and view all the answers

    Which clause in the construction contract covers the search for defects not caused by the contractor's fault?

    <p>Search for defects not caused by the contractor's fault</p> Signup and view all the answers

    Study Notes

    Construction Contract Clause Summary

    • The text is a detailed summary of various clauses in a construction contract, including potential events that could lead to entitlement for additional time and costs.
    • It covers clauses related to variations in the project, exceptional climatic conditions, shortages in personnel or goods due to epidemic or government action, delays or prevention by the employer or other contractors, and measured quantity of items exceeding estimates.
    • It also discusses clauses related to suspension instructed by the employer, interference with tests on completion, delayed access after taking over, and search for defects not caused by the contractor's fault.
    • The summary includes clauses related to contractor's failure to provide assistance or comply with permits, errors in contractor's documents, delays in tests, retests due to defects, and remedial work by the employer.
    • It details clauses related to measures to overcome slow progress, failure to complete within the specified time, delayed tests on completion, and failed tests on completion.
    • The summary also covers clauses related to the inability to use a section of the works due to a defect, failure to rectify a defect, failure to clear the site, and failure of tests after completion.
    • It compares the total claim events for different types of contracts - Red, Yellow, Silver, and Emerald.
    • The text also includes "other matters" referred to the engineer for agreement/determination under the contract, including reduction in delay damages due to taking over of a part and the cause of a defect.
    • It details measurement of the works, rate or price for valuation, EOT/adjustments to contract price due to variation by engineer instruction, resources used in executing a variation, and revision of schedule of payments not based on progress.
    • The summary provides a comprehensive overview of the clauses and entitlements in the construction contract, emphasizing the potential events and circumstances that could impact time and costs.
    • It includes a comparison of claim events across different types of contracts and highlights the "other matters" referred to the engineer for agreement/determination under the contract.
    • The summary is a detailed guide to understanding the various clauses, entitlements, and processes outlined in the construction contract.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Explore a detailed summary of the various clauses in a construction contract, including entitlements for additional time and costs. The summary provides a comprehensive overview of clauses, entitlements, and processes, alongside a comparison of claim events across different types of contracts.

    More Like This

    R 99 - 10
    44 questions

    R 99 - 10

    AstoundedHamster avatar
    AstoundedHamster
    Y 99 - 2
    24 questions

    Y 99 - 2

    AstoundedHamster avatar
    AstoundedHamster
    S 99 - 4
    30 questions

    S 99 - 4

    AstoundedHamster avatar
    AstoundedHamster
    Use Quizgecko on...
    Browser
    Browser