Questions and Answers

Which class of cost estimate is performed at the functional program phase?

  • Class B
  • Class C
  • Class D (correct)
  • Class A

At what project phase is the Class C cost estimate performed?

  • Construction phase
  • Schematic design phase (correct)
  • Functional program phase
  • Design development phase

Which class of cost estimate has the greatest accuracy?

  • Class C
  • Class A (correct)
  • Class D
  • Class B

Which factor can significantly influence construction costs in Canada?

<p>Site characteristics (A)</p> Signup and view all the answers

What is one of the features that can affect the cost of a building?

<p>Compliance with building codes (A)</p> Signup and view all the answers

Which stakeholder group may have restrictions on procurement methods due to regulations and key stakeholder interest and influence?

<p>Government agencies and public institutions (C)</p> Signup and view all the answers

What is the purpose of the functional program in the design project?

<p>To define the owner's and users' functional requirements (D)</p> Signup and view all the answers

Which cost estimate class is performed near or at completion of the construction document phase?

<p>Class A (C)</p> Signup and view all the answers

What is the estimating range for Class B cost estimate?

<p>±10% and ±15% (A)</p> Signup and view all the answers

What are the advantages of Class A cost estimate?

<p>Information stays current and relevant throughout pre-construction (C)</p> Signup and view all the answers

What factors can affect construction costs?

<p>Inflation, market conditions, and economic factors (D)</p> Signup and view all the answers

Which of the following may be a result of a functional program that was not validated against the construction cost estimate?

<p>The architect may be expected to make design adjustments without additional fees or extending the schedule. (B)</p> Signup and view all the answers

What are some reasons for changes in the scope of a project?

<p>The development of more specific, detailed requirements by the owner. (C)</p> Signup and view all the answers

How can contractual relationships between the owner and the contractor impact the cost of a project?

<p>They can affect the construction budget. (C)</p> Signup and view all the answers

What are some factors that can affect the construction budget?

<p>Regulatory and by-law requirements. (D)</p> Signup and view all the answers

Flashcards are hidden until you start studying

More Like This

Challenges in Conventional Construction
5 questions
BIM in Construction: Challenges and Solutions
8 questions
2D Design Principles
37 questions

2D Design Principles

SilentMeteor5959 avatar
SilentMeteor5959
Use Quizgecko on...
Browser
Browser