What was the primary risk identified in the project described?
What was the primary risk identified in the project described?
The primary risk was miscommunication that could disrupt lab activities.
What communication tool was created to provide clarity regarding restricted areas and equipment locations?
What communication tool was created to provide clarity regarding restricted areas and equipment locations?
A detailed schedule and site map was created.
Name one of the actions taken to ensure stakeholders were informed about the project.
Name one of the actions taken to ensure stakeholders were informed about the project.
A kickoff meeting was organized or follow-up emails were sent summarizing key outcomes.
What specific scheduling issue was encountered during the project?
What specific scheduling issue was encountered during the project?
Signup and view all the answers
What vendor is explicitly mentioned as a major supplier?
What vendor is explicitly mentioned as a major supplier?
Signup and view all the answers
What was the main objective of the project?
What was the main objective of the project?
Signup and view all the answers
What did the project learn about adapting communication methods?
What did the project learn about adapting communication methods?
Signup and view all the answers
What were the project's main success criteria?
What were the project's main success criteria?
Signup and view all the answers
What was the primary issue that led to the lab's account with BOC being blocked?
What was the primary issue that led to the lab's account with BOC being blocked?
Signup and view all the answers
What crucial action did the author take to separate the lab's finances from Mars Wrigley?
What crucial action did the author take to separate the lab's finances from Mars Wrigley?
Signup and view all the answers
Who were the key stakeholders involved in addressing the issue with BOC?
Who were the key stakeholders involved in addressing the issue with BOC?
Signup and view all the answers
Besides outlining the problem, what was the other key objective for the initial stakeholder engagement meetings?
Besides outlining the problem, what was the other key objective for the initial stakeholder engagement meetings?
Signup and view all the answers
What was the main goal behind inviting BOC representatives for a site visit?
What was the main goal behind inviting BOC representatives for a site visit?
Signup and view all the answers
What were the key actions during weekly meetings with stakeholders to ensure progress?
What were the key actions during weekly meetings with stakeholders to ensure progress?
Signup and view all the answers
How was the meeting time adjusted to accommodate the various stakeholders?
How was the meeting time adjusted to accommodate the various stakeholders?
Signup and view all the answers
What was the result of the project in terms of the lab's financial status and communication?
What was the result of the project in terms of the lab's financial status and communication?
Signup and view all the answers
What is crucial for aligning stakeholders and minimizing disruptions?
What is crucial for aligning stakeholders and minimizing disruptions?
Signup and view all the answers
What type of event was planned to strengthen collaboration, understanding, and relationships within a diverse team?
What type of event was planned to strengthen collaboration, understanding, and relationships within a diverse team?
Signup and view all the answers
What was a key consideration when planning the team-building event to ensure inclusivity?
What was a key consideration when planning the team-building event to ensure inclusivity?
Signup and view all the answers
What specific tool was used to identify team members' strengths and weaknesses during the team-building event?
What specific tool was used to identify team members' strengths and weaknesses during the team-building event?
Signup and view all the answers
Besides the Belbin assessment, what other type of activity was included in the team-building event to foster personal connection?
Besides the Belbin assessment, what other type of activity was included in the team-building event to foster personal connection?
Signup and view all the answers
Name one way the event organizer ensured the team felt valued during the event?
Name one way the event organizer ensured the team felt valued during the event?
Signup and view all the answers
How did the event organizer use observations of team members to improve team performance?
How did the event organizer use observations of team members to improve team performance?
Signup and view all the answers
What specific action did Will take after the team-building event to improve team performance?
What specific action did Will take after the team-building event to improve team performance?
Signup and view all the answers
What was the primary responsibility of the individual in the First Aid (FA) team leadership role?
What was the primary responsibility of the individual in the First Aid (FA) team leadership role?
Signup and view all the answers
How did the FA team leader ensure the team was well-prepared for their roles during the recruitment process?
How did the FA team leader ensure the team was well-prepared for their roles during the recruitment process?
Signup and view all the answers
What approach did the FA team leader take to improve the performance of a member not answering FA phones regularly?
What approach did the FA team leader take to improve the performance of a member not answering FA phones regularly?
Signup and view all the answers
What was the effect of the FA team leader's actions on the underperforming team member?
What was the effect of the FA team leader's actions on the underperforming team member?
Signup and view all the answers
What was one key change learned during the FA team leadership role?
What was one key change learned during the FA team leadership role?
Signup and view all the answers
Why did the FA team leader assign members to sub-teams?
Why did the FA team leader assign members to sub-teams?
Signup and view all the answers
What was the purpose of the monthly and quarterly meetings led by the FA team leader?
What was the purpose of the monthly and quarterly meetings led by the FA team leader?
Signup and view all the answers
Besides leading the FA team, what other responsibility did this leader manage?
Besides leading the FA team, what other responsibility did this leader manage?
Signup and view all the answers
What was the main objective while servicing lab equipment?
What was the main objective while servicing lab equipment?
Signup and view all the answers
What was the purpose of implementing a 24-hour stabilization period for the balances?
What was the purpose of implementing a 24-hour stabilization period for the balances?
Signup and view all the answers
How was scheduling miscommunication regarding roof access and fire sensor isolation resolved?
How was scheduling miscommunication regarding roof access and fire sensor isolation resolved?
Signup and view all the answers
How was the first week of the pipette clinic impacted by the actions taken?
How was the first week of the pipette clinic impacted by the actions taken?
Signup and view all the answers
What was the approximate weight of the freezer in the situation described?
What was the approximate weight of the freezer in the situation described?
Signup and view all the answers
Besides fire sensor isolation, what other safety measure was put in place?
Besides fire sensor isolation, what other safety measure was put in place?
Signup and view all the answers
What were associates asked to follow when they made unrelated requests?
What were associates asked to follow when they made unrelated requests?
Signup and view all the answers
What were two of the key learnings mentioned regarding managing multiple stakeholders and tight deadlines?
What were two of the key learnings mentioned regarding managing multiple stakeholders and tight deadlines?
Signup and view all the answers
What proactive step was taken to address the lorry driver's lack of training?
What proactive step was taken to address the lorry driver's lack of training?
Signup and view all the answers
Beyond just completing the task of delivering the freezer, what additional goal was emphasized throughout the described process?
Beyond just completing the task of delivering the freezer, what additional goal was emphasized throughout the described process?
Signup and view all the answers
What method was used to inform the entire site about the upcoming freezer delivery and potential disruptions?
What method was used to inform the entire site about the upcoming freezer delivery and potential disruptions?
Signup and view all the answers
What was one of the key takeaways from the freezer delivery project related to potential issues that may arise?
What was one of the key takeaways from the freezer delivery project related to potential issues that may arise?
Signup and view all the answers
What specific action showed an effort to understand the new lab environment after switching departments?
What specific action showed an effort to understand the new lab environment after switching departments?
Signup and view all the answers
Why was it important to network with the new lab team, besides getting to know new people?
Why was it important to network with the new lab team, besides getting to know new people?
Signup and view all the answers
What was one of the main reasons it was important to provide participant-specific communication regarding the freezer move?
What was one of the main reasons it was important to provide participant-specific communication regarding the freezer move?
Signup and view all the answers
What was the stated reason that delaying a task is permissible, in order to ensure safety?
What was the stated reason that delaying a task is permissible, in order to ensure safety?
Signup and view all the answers
Study Notes
Collaborates: Building Partnerships
- Building partnerships with others to meet shared objectives
- Unpaid invoices blocked lab's account with BOC, impacting lab, Vet, and Research teams, as well as BOC
- Lab and Mars Wrigley site were under the same financial umbrella, creating invoice management issues
- Initiated a project to separate the lab's financial entity to prevent recurring issues and rebuild trust with BOC
Stakeholder Engagement
- Organized meetings with key stakeholders (BOC, Mars, and Ariba teams) to outline the problem, gather pain points, and propose objectives
- Ensured alignment with stakeholders
- Invited BOC representatives for a site visit to build rapport and trust
Building Trust
- Invited BOC representatives for site visit to understand lab's work and build rapport and trust
Process Management
- Scheduled and led weekly meetings with BOC, Mars, and financial representatives to address outstanding invoices
- Captured minutes and set clear, actionable next steps
- Ensured mutual agreement on actions and timelines
- Escalated unresolved items when necessary to maintain momentum
Collaboration And Flexibility
- Adjusted meeting times from 9 a.m. to 1 p.m. to accommodate stakeholder availability
Result
- Successfully separated lab as a distinct financial entity under "Petcare"
- Reduced contacts from six to three to streamline communication
- Unblocked lab accounts, restoring purchasing capabilities
- Improved efficiency
- Cleared 50% of outstanding ledger invoices
Learnings
- Importance of regular review and accountability to prevent delays in projects
- Adapting communication methods to team needs is crucial to maintaining engagement
Communicated Effectively
- Developed and delivered multi-mode communications to understand the unique needs of different audiences
Situation: Engineering Project
- Facilitated an engineering project involving lab fume hood servicing, coordinating with engineers, lab users and external vendors
- Overlapping projects, tight deadlines, and risk of miscommunication
- Ensured all stakeholders informed, aligned, and able to collaborate effectively
- Maintained safety and minimized disruption while delivering project on time
Action: Engineering Project
- Organized kickoff meetings with stakeholders (lab users and facilities) to discuss objectives, schedules, and dependencies
- Created a visual communication tool (schedule and site map) to outline restricted areas and movement paths
- Sent advanced notices to lab users to inform about temporary restrictions and changes in workflows
- Regularly checked with stakeholders, resolving any issues promptly, and using effective delegation (e.g. assigning lab owners to guide engineers)
Result: Engineering Project
- Successfully serviced all lab fume hood equipment in the set timeframe
- Clear and effective communication maintained alignment and avoided confusion
Interpersonal Savvy: Relating with Diverse Groups
- Planned an FA team-building event for 15 members across all levels (operations, research, labs and facilities)
- Ensured inclusivity, accommodating everyone's schedules and maintaining safety
- Strengthened teams, fostered collaboration
- Initiated and led the planning process to ensure inclusivity and engagement
- Organized resources, including catering, and encouraged SM to involve the team in decisions
- Suggested personal and professional activities (Belbin assessment, storytelling)
- Observed team members, evaluated strengths/weaknesses, and reallocated team members into subgroups based on aligned efforts
Result: Interpersonal Savvy
- Strengthened team dynamics
- Improved performance, alignment of strengths to roles
- Increased cohesion & collaboration
- Open communication and recognition
- Learned importance of balancing physical and interactive activities for engagement
Ensures Accountability: Holding Self and Others Accountable
- Part of the First Aid team for five years and leader since January 2024
- Ensured team is well prepared for any FA situations
- Established a strong team culture, starting from recruitment
- Team members understand responsibilities and committed to maintaining safety
- Engages, motivates, and holds team members accountable for consistent performance
Action: Ensures Accountability
- Clearly outlined FA responsibilities and expectations during recruitment
- Assigned members to sub-teams based on strengths/weaknesses/objectives
- Leads monthly and quarterly meetings to review FA findings, discuss improvements, and assign actionable tasks
- Analyzed KPI data and assigned tasks to maintain progress
Result: Ensures Accountability
- Team meets or exceeds expectations
- FA team members consistently meet expectations
Manages Complexity
- Making sense of complex, high quantity and sometimes contradictory information to effectively solve problems
Planning & Scheduling
- Developed detailed schedules, ensured cleanliness protocols, and prioritized equipment servicing
Communication & Delegation
- Communicated clear expectations to the team, delegated tasks effectively, and ensured smooth facilitation
Problem-Solving
- Resolved scheduling miscommunications
- Issued work permits, arranged fire sensor isolation, scheduled fire marshall rotations
Handling Competing Priorities
- Addressed unrelated requests by guiding associates
- Asked probing questions to determine urgency
Result: Planning & Scheduling, Communication, Problem-Solving, Handling Competing Priorities
- Successfully facilitated servicing of 26 fume hoods in 5 days, followed a schedule, and avoided disruptions
Key Learning: Planning & Scheduling, Communication, Problem-Solving, Handling Competing Priorities
Reduced Chemical Disposal Visits
- Reduced chemical disposal visits from 3 hours to 1 hour by preplanning, requesting data and encouraging team alignments
Enhanced Collaboration
- Enhanced collaboration between operations and labs, leading to smoother workflows
Interview Qs:
- Objectives and development needs
- Potential challenges in first six months
- Areas for elaboration on previous discussions
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz focuses on the importance of building partnerships and trust among stakeholders, particularly in the context of managing financial issues and fostering collaboration. Participants will explore strategies for engaging key parties, managing processes, and ensuring alignment to achieve shared objectives.