Podcast
Questions and Answers
What is the minimum recommended percentage of spare conductors to leave for cables carrying 5 or more pairs of conductors?
What is the minimum recommended percentage of spare conductors to leave for cables carrying 5 or more pairs of conductors?
- 75%
- 25% (correct)
- 10%
- 50%
When deciding the route for cable installation, which of the following approaches is recommended?
When deciding the route for cable installation, which of the following approaches is recommended?
- Using GPS for route planning
- Walking along the track to assess best alignment (correct)
- Following the existing power cable layout
- Consulting a map only
What should be used to determine the location for laying telecom cables in relation to the railway track?
What should be used to determine the location for laying telecom cables in relation to the railway track?
- Local traffic signs
- Existing cable routes
- Boundary pillars (correct)
- A GPS device
At what distance should telecom cables be laid away from the nearest track?
At what distance should telecom cables be laid away from the nearest track?
What is the purpose of cable markers along the cable route?
What is the purpose of cable markers along the cable route?
What additional care must be taken during cable installation in alluvial soil?
What additional care must be taken during cable installation in alluvial soil?
What is the nominal interval at which cable markers should be provided along the route?
What is the nominal interval at which cable markers should be provided along the route?
Which type of marking is specified for the Quad cable RCC route marker?
Which type of marking is specified for the Quad cable RCC route marker?
What is the minimum depth at which a cable should be laid below ground?
What is the minimum depth at which a cable should be laid below ground?
What is the standard distance to maintain between the nearest edge of the cable trench and an OHE mast when the trench exceeds 0.5 m in depth?
What is the standard distance to maintain between the nearest edge of the cable trench and an OHE mast when the trench exceeds 0.5 m in depth?
How far must cables be laid from a metallic body of a traction sub-station?
How far must cables be laid from a metallic body of a traction sub-station?
What is the required spacing between signalling and telecommunication cables when laid in the same trench?
What is the required spacing between signalling and telecommunication cables when laid in the same trench?
What action must be taken if the cable depth cannot exceed 0.5 m due to local conditions?
What action must be taken if the cable depth cannot exceed 0.5 m due to local conditions?
When laying cables across tracks, what is the minimum depth required below the rail flanges?
When laying cables across tracks, what is the minimum depth required below the rail flanges?
What is the minimum distance maintainable from a station earthing when laying cables in the vicinity of OHE switching stations?
What is the minimum distance maintainable from a station earthing when laying cables in the vicinity of OHE switching stations?
What is a general standard distance for laying cables outside station limits from the center of the nearest track?
What is a general standard distance for laying cables outside station limits from the center of the nearest track?
How should the bending radius be maintained for aluminium sheathed armoured cables?
How should the bending radius be maintained for aluminium sheathed armoured cables?
What should be used to mark the position of cable joints on the nearest OHE mast?
What should be used to mark the position of cable joints on the nearest OHE mast?
What should be taken into account when planning the cable allocation on a route?
What should be taken into account when planning the cable allocation on a route?
How should the desired cable route be visually represented?
How should the desired cable route be visually represented?
What is a critical distance requirement when laying telecom cables adjacent to the nearest track?
What is a critical distance requirement when laying telecom cables adjacent to the nearest track?
What should be done before making trenches in the vicinity of track formation areas?
What should be done before making trenches in the vicinity of track formation areas?
How should the cable markers along the route be designed?
How should the cable markers along the route be designed?
What is the recommended action regarding spare conductors when planning cabling?
What is the recommended action regarding spare conductors when planning cabling?
What consideration should be made regarding the existing routes when planning the cable route?
What consideration should be made regarding the existing routes when planning the cable route?
What element should be prioritized when laying cables during the monsoon season?
What element should be prioritized when laying cables during the monsoon season?
What is the minimum distance that should be maintained between the cable and an OHE mast when the depth of the cable trench is limited to 0.5 m?
What is the minimum distance that should be maintained between the cable and an OHE mast when the depth of the cable trench is limited to 0.5 m?
What specific condition allows the distance between cables and station earthing to be reduced to one meter?
What specific condition allows the distance between cables and station earthing to be reduced to one meter?
What is the required distance between telecommunication cables and HT or LT power cables when laid in the same trench?
What is the required distance between telecommunication cables and HT or LT power cables when laid in the same trench?
How far from the center of the nearest track should cables be laid outside station limits?
How far from the center of the nearest track should cables be laid outside station limits?
What is the maximum allowable bending radius for aluminium sheathed armoured cables?
What is the maximum allowable bending radius for aluminium sheathed armoured cables?
What is the depth requirement for cables laid across the track relative to the rail flanges?
What is the depth requirement for cables laid across the track relative to the rail flanges?
What method should be used for laying cables over rocky terrain?
What method should be used for laying cables over rocky terrain?
When cables are laid along girder bridges, what special consideration is mentioned?
When cables are laid along girder bridges, what special consideration is mentioned?
What is the minimum distance to maintain from a metallic body of a traction sub-station when laying cables?
What is the minimum distance to maintain from a metallic body of a traction sub-station when laying cables?
What additional requirement is specified when cables are laid in the vicinity of OHE switching stations?
What additional requirement is specified when cables are laid in the vicinity of OHE switching stations?
What is the primary consideration when planning the number of conductors for a cable?
What is the primary consideration when planning the number of conductors for a cable?
Why is it recommended to leave 25% or more conductors spare in cables with 5 or more pairs?
Why is it recommended to leave 25% or more conductors spare in cables with 5 or more pairs?
How should the desired cable route be visually represented?
How should the desired cable route be visually represented?
When laying telecom cables, what is the minimum distance to be maintained from the nearest track?
When laying telecom cables, what is the minimum distance to be maintained from the nearest track?
What is the purpose of cable markers along the cable route?
What is the purpose of cable markers along the cable route?
What special care should be taken during the installation of cables in alluvial soil?
What special care should be taken during the installation of cables in alluvial soil?
At what nominal interval should cable markers be placed along the route?
At what nominal interval should cable markers be placed along the route?
What color should the Quad cable RCC route marker be painted?
What color should the Quad cable RCC route marker be painted?
What is the minimum distance that should be maintained between a cable and the OHE mast in exceptional cases where the trench depth is limited to 0.5 m?
What is the minimum distance that should be maintained between a cable and the OHE mast in exceptional cases where the trench depth is limited to 0.5 m?
What is the required depth for cables laid across the track in relation to the rail flanges?
What is the required depth for cables laid across the track in relation to the rail flanges?
What is the minimum distance to be maintained from any metallic body of a traction sub-station when laying cables?
What is the minimum distance to be maintained from any metallic body of a traction sub-station when laying cables?
What should be done if the cable cannot be laid at least 1 meter above the ground due to local conditions?
What should be done if the cable cannot be laid at least 1 meter above the ground due to local conditions?
What is the recommended distance to maintain between signalling and telecommunication cables when laid in the same trench?
What is the recommended distance to maintain between signalling and telecommunication cables when laid in the same trench?
How deep should the trench be for telecommunication cables compared to power cables?
How deep should the trench be for telecommunication cables compared to power cables?
What action must be taken to ensure safe laying of cables in the vicinity of traction sub-stations?
What action must be taken to ensure safe laying of cables in the vicinity of traction sub-stations?
What is the minimum distance from a traction sub-station earthing when laying cables?
What is the minimum distance from a traction sub-station earthing when laying cables?
What is the bending radius requirement for laying aluminium sheathed armoured cables?
What is the bending radius requirement for laying aluminium sheathed armoured cables?
When laying cables in the vicinity of OHE switching stations, what is the minimum distance to be maintained from the station earthing?
When laying cables in the vicinity of OHE switching stations, what is the minimum distance to be maintained from the station earthing?
Flashcards are hidden until you start studying
Study Notes
Cabling Planning & Route Selection
- Determine the number of conductors, cable size and type needed (quad/PIJF) based on desired circuit type.
- Zonal Railway may allocate quad on the 6Q including BPAC/IBS.
- A 25% or more conductor spare is recommended for cables with 5 or more pairs, due to long cable lifespan and future expansion needs.
- Choose the best cable route by walking/travelling along the track and identifying the optimal alignment.
- Clearly depict the chosen route on a route plan, showing track alignment, offsets from permanent structures, and crossings (road, track, power cables, water and sewage mains).
- Existing power cable routes and other relevant information should be included on the route plan.
- Identify convenient distribution points for connecting main cables to smaller distribution cables (e.g., subscriber cabling for exchange, emergency socket locations).
- Telecommunication cables should generally be laid within 1 meter inside the Railway boundary (refer to boundary pillars or, if absent, contact P.Way/works officials).
- Maintain a minimum distance of 2 meters from the nearest track and beyond embankment.
- Trench work within the formation area of the track should be done only after consultation with P.Way staff and filled/rammed properly before sunset on the same day.
- Ensure separation of at least 1 meter between telecommunication cable and nearest electrical power cable.
Cable Marker Placement & Depth
- Provide cable markers at 50 meter intervals along the route.
- Additional markers should highlight important points like cable joints, water and sewage mains, power cable crossings, alignment bends/curves.
- Use Quad cable RCC route marker (Drawing no.RDSO/TCDO/COP-22(a) in chapter XIII, painted red).
- Paint Quad cable joint markers yellow on all sides for easy identification.
- Bury the cable at least 1 meter below ground level.
- Ensure sufficient trench width for easy cleaning and cable laying.
Special Considerations Near OHE & Other Structures
- In yards or where trench depth is limited to 0.5 meters, maintain a minimum of 1 meter distance between cable and OHE mast supporting the catenary or other structures likely to come in contact with high tension conductors.
- If the 1 meter distance cannot be maintained, lay the cable in concrete pipes to reduce the required distance to 0.5 meters.
- When trench depth exceeds 0.5 meters near OHE masts, ensure the nearest edge of the trench is at least 3 meters away from the mast.
- Mark cable joint positions on the nearest OHE mast with an approved legend.
Cable Laying in Vicinity of Substations & OHE Switching Stations
- In vicinity of traction substations, lay cable at least 1 meter away from any metallic body fixed in the ground and 1 meter away from substation earthing.
- Lay cables in concrete pipes/enclosed brick channels for 300 meters on both sides of the substation.
- Preferably lay cable on the track side opposite the substation.
- Near OHE switching stations, lay the cable at least 1 meter away from any metallic body fixed in the ground and 5 meters away from station earthing.
- Reduce the 5 meter distance from station earthing to 1 meter if the cables are laid in concrete piles.
- Lay cables at least 1 meter away from independent earthing provided for OHE structures.
General Cable Spacing & Laying Practices
- Outside station limits, lay cables at a standard distance of 10 meters from the center of the nearest track.
- When laying signalling and telecommunication cables in the same trench, maintain a 100 mm distance using bricks at 2-meter intervals.
- Do not lay HT, LT power cables and telecommunication cables in the same trench.
- Bury cables parallel to the track 1 meter below the ground, and those laid across the track 1 meter below rail flanges.
- Keep the telecommunication cable trench as far away as possible from the power cable trench.
- Follow approved methods for laying cables along girder bridges, over culverts, through culvert beds, over rocky terrain, etc.
- Avoid sharp bends in cables during laying.
- Ensure bending radius for aluminium sheathed armoured cables is at least 40 times the cable diameter.
- Generally lay OFC and quad cables in the same trenches (refer to chapter XIII for drawings).
Cable Planning and Laying
- Cable Type and Quantity: Determine the number of conductors, sizes, and cable type (quad/PIJF) based on circuit requirements. Zonal Railways may allocate quad on the 6Q for BPAC/IBS.
- Future Expansion: Reserve at least 25% of conductors for future expansion in cables with 5 or more pairs, considering their long lifespan.
- Route Planning:
- Route Selection: Walk or travel along the track to identify the best alignment for the cable route.
- Route Diagram: Create a route plan showing the alignment, offsets from permanent structures, crossings (road, track, power cable, water and sewage mains), and other important points.
- Distribution Points: Choose convenient locations for cable distribution (main cable to smaller cables for subscribers, emergency sockets, etc.).
- Cable Layout:
- Railroad Boundary: Lay telecom cables within 1 meter of the railway boundary.
- Distance from Track: Maintain at least 2 meters from the nearest track and beyond the embankment.
- Trenches:
- Consult with P.Way staff before digging trenches in or near the track formation area.
- Fill and compact trenches immediately after laying cables, especially during monsoon season and in alluvial soil.
- Ensure at least 1 meter separation from electrical power cables.
- Cable Markers:
- Use cable markers at 50-meter intervals.
- Include markers for cable joints, water and sewage mains, power cable crossings, alignment bends/curves, etc.
- Use RDSO/TCDO/COP-22(a) markers painted red, with yellow enamel for quad cable joints.
- Cable Depth:
- General depth: Lay cables at least 1 meter below the surface.
- Limited Depth: Maintain at least 1 meter between the cable and overhead equipment (OHE) masts when depth is limited to 0.5 meters.
- Deep Trenches: Maintain at least 3 meters between the OHE mast and the nearest edge of the cable trench when depth exceeds 0.5 meters.
- Cable Joints: Mark cable joint positions on the nearest OHE mast using approved legend.
- Vicinity of Substations and OHE Stations:
- Traction Substations:
- Lay cables at least 1 meter from metallic bodies and substation earthing systems.
- Utilize concrete pipes or brick channels for 300 meters on either side of the substation.
- Prefer laying on the track side opposite the substation.
- OHE Switching Stations:
- Lay cables at least 1 meter from metallic bodies and 5 meters from station earthing.
- The 5-meter distance can be reduced to 1 meter if the cables are laid in concrete piles.
- OHE Structures: Lay cables at least 1 meter from independent earthings for OHE structures.
- Traction Substations:
- Cable Laying Outside Stations: Maintain a standard distance of 10 meters from the center of the nearest track.
- Signaling and Telecommunication Cables:
- Maintain 100 mm distance between signaling and telecommunication cables in the same trench using bricks at 2-meter intervals.
- Do not lay HT/LT power cables and telecommunication cables in the same trench.
- Cable Depth Relative to Track: Lay cables parallel to the track at 1.0 meter depth, and across the track at 1.0 meter below rail flanges.
- Power and Telecommunication Cable Trench Spacing: Keep power and telecommunication cable trenches as far apart as possible.
- Special Laying Conditions: Follow approved methods for laying cables along girder bridges, over culverts, through culvert beds, over rocky terrain, etc.
- Cable Bends: Avoid sharp bends. Minimum bending radius should be 40 times the cable diameter for aluminum-sheathed armored cables.
- Laying OFC and Quad Cables: Usually laid in the same trench, refer to Chapter XIII for drawings and specifications.
Cable Planning
- The number and size of conductors, and the type of cable required should be determined first based on the type of circuits desired.
- Zonal Railway may issue an allocation of quads, BPAC/IBS, etc. on the 6Q.
- Leave 25% or more conductors spare for all cables carrying 5 or more pairs of conductors for future expansion.
- Cables should be laid within 1 meter inside the Railway boundary, 2 meters away from the nearest track and beyond the embankment.
- Consult with P.Way staff before digging trenches near the formation area of the track.
- Fill in trenches and ram them after laying the cables on the same day before sunset.
- Ensure trenches are at least 1 meter away from electrical power cables.
- Cable markers should be provided every 50 meters along the route.
- Use a Quad cable RCC route marker as per Drawing no. RDSO/TCDO/COP-22(a) available at chapter XIII.
- Paint the markers red and use yellow enamel paint on all sides of the RCC cable marker above ground to identify quad joints.
- Cable should be buried at least 1 meter below the surface of the ground.
- Ensure the trench is wide enough for smooth cleaning and laying of cables.
- In yards, maintain a minimum distance of one meter between the cable and the OHE mast, and ensure the cable is laid in concrete pipes when this rule is difficult to observe.
- When the depth of the cable trench exceeds 0.5 meters near OHE masts, ensure the nearest edge of the cable trench is at least 3 meters away from the OHE mast.
- Mark the position of cable joints on the nearest OHE mast by painting an approved legend.
- When laying cables in the vicinity of traction substations, OHE switching stations, and their associated earthing system, ensure the cable is laid at least one meter away from any metallic body of the station which is fixed in the ground.
- Ensure the cable is laid at least one meter away from the substation earthing.
- Lay the cables in concrete pipes or enclosed brick channels for a length of 300 meters on either side of the substation.
- Lay cables on the side of the track opposite the substation side.
- Ensure cables are laid at least one meter away from any metallic body of the OHE switching station which is fixed in the ground.
- Lay cables at least 5 meters away from station earthing.
- The distance of 5 meters from station earthing can be reduced to one meter if the cables are laid in concrete piles.
- Ensure cables are laid at least one meter away from the independent earth provided for an OHE structure.
- Outside station limits, the cable should be laid a standard distance of 10 meters from the center of the nearest track.
- When laying signalling and telecommunication cables in the same trench, maintain a distance of about 100 mm between them by placing bricks at intervals of two meters.
- Do not lay HT and LT power cables and telecommunication cables in the same trench.
- When cables are laid parallel to the track, ensure they are buried at a depth of 1.0 meters.
- When cables are laid across the track, ensure they are buried one meter below the rail flanges.
- Keep the trench for telecommunication cables as far away as possible from the trench for the power cables.
- For laying cables along girder bridges, over culverts, through the bed of culverts, over rocky terrain, and other such locations, lay the cables as per approved methods for each location.
- Do not subject cables to sharp bends.
- Ensure the bending radius for the cable is at least 40 times the diameter of the cable in case of aluminium sheathed armoured cables.
- OFC and quad cables can be laid in the same trenches.
- Refer to chapter XIII for drawings on laying OFC/quad cables.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.