S 2017 - 4
25 Questions
2 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the Contractor required to submit before the Tests on Completion?

  • Provisional O&M Manuals (correct)
  • Schedule of Performance Guarantees
  • Inventory of spare parts
  • Final O&M Manuals
  • When should the Contractor rectify errors or defects found in the provisional O&M Manuals?

  • During the Tests on Completion (correct)
  • At the Employer's risk and cost
  • Before the issue of Taking-Over Certificate
  • After the submission of final O&M Manuals
  • In case of errors found in the Contractor's design and/or documents, how should they be corrected?

  • By resubmitting to the Employer
  • By rejecting the Works
  • In accordance with Sub-Clause 7.5 Defects (correct)
  • By obtaining a Notice of No-objection
  • When should the final O&M Manuals be submitted to the Employer?

    <p>Before the issue of any Taking-Over Certificate</p> Signup and view all the answers

    Who is responsible for engaging and paying all personnel, their accommodation, transport, and welfare?

    <p>The Contractor</p> Signup and view all the answers

    What becomes the property of the Employer upon delivery to the site or payment to the Contractor?

    <p>Plant and materials</p> Signup and view all the answers

    In what circumstances can the Employer employ and pay others for the work with costs borne by the Contractor?

    <p>If the Contractor fails to comply with instructions</p> Signup and view all the answers

    Who is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials?

    <p>The Contractor</p> Signup and view all the answers

    What must the Employer give not less than 14 days before the Commencement Date?

    <p>Notice of the Commencement Date</p> Signup and view all the answers

    Who is responsible for design errors and all corrections and resubmissions at their own risk and cost?

    <p>The Contractor</p> Signup and view all the answers

    What happens if Plant and/or Materials delivery is suspended for more than 28 days?

    <p>Specific conditions apply for marking and evidencing compliance</p> Signup and view all the answers

    Under what circumstances can the Contractor request permission to proceed if the suspension of work continues for more than 84 days?

    <p>If the suspension continues for more than 84 days</p> Signup and view all the answers

    What must the Contractor comply with regarding wages and labor conditions?

    <p>Laws and standards</p> Signup and view all the answers

    Under what circumstances can the Employer employ and pay others for the work with costs borne by the Contractor?

    <p>If the Contractor fails to comply with instructions</p> Signup and view all the answers

    What specific provision applies for suspension and evidence of compliance if the Contractor fails to comply with instructions?

    <p>Specific provisions for suspension and evidence of compliance</p> Signup and view all the answers

    Who is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials?

    <p>The Contractor</p> Signup and view all the answers

    What happens if the Employer does not give a Notice within 14 days after receiving the test results?

    <p>The Employer shall be deemed to have given a Notice of No-objection</p> Signup and view all the answers

    What action can the Employer take if the Tests on Completion are unduly delayed by the Contractor?

    <p>Require the Contractor to carry out the tests within 21 days</p> Signup and view all the answers

    What happens if the Contractor fails to carry out the Tests on Completion within the specified period?

    <p>The Employer's Personnel may proceed with the tests</p> Signup and view all the answers

    What is the consequence if the Works fail to pass the Tests on Completion?

    <p>The Employer may order further repetition of Tests on Completion</p> Signup and view all the answers

    What provision applies if the Works fail to pass the Tests on Completion and need to be repeated?

    <p>Sub-Clause 7.5 [Defects and Rejection]</p> Signup and view all the answers

    What is the consequence if the Works fail to pass the Tests on Completion repeated under Sub-Clause 9.3 [Retesting]?

    <p>The Employer may order further repetition of Tests on Completion</p> Signup and view all the answers

    What becomes of the repeated tests under Sub-Clause 9.3 [Retesting]?

    <p>Treated as Tests on Completion for the purposes of the Clause</p> Signup and view all the answers

    What is the Employer entitled to if the Works fail to pass the Tests on Completion repeated under Sub-Clause 9.3 [Retesting]?

    <p>Payment of the costs reasonably incurred</p> Signup and view all the answers

    What happens if the Tests on Completion are unduly delayed by the Employer's Personnel or due to a cause for which the Employer is responsible?

    <p>Sub-Clause 10.3 [Interference with Tests on Completion] applies</p> Signup and view all the answers

    Study Notes

    FIDIC 2017 EPC/Turnkey Contract - Key Clauses Summary

    • The Contractor is responsible for engaging and paying all personnel, their accommodation, transport, and welfare, unless otherwise stated in the Specification.
    • The Contractor must comply with laws and standards for wages and labor conditions, and cannot recruit the Employer's personnel.
    • If the Contractor fails to comply with instructions, the Employer may employ and pay others for the work, with costs borne by the Contractor.
    • Plant and materials become the property of the Employer upon delivery to the site, payment to the Contractor, or as determined under specific sub-clauses.
    • The Contractor is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials.
    • The Employer must give a notice of the Commencement Date not less than 14 days before the date, unless otherwise stated in the Particular Conditions.
    • The Contractor must complete the works within the agreed Time for Completion, with specific provisions for suspension and evidence of compliance.
    • If Plant and/or Materials delivery is suspended for more than 28 days, specific conditions apply for marking and evidencing compliance.
    • If the suspension continues for more than 84 days, the Contractor may request permission to proceed, and if not granted, may terminate the contract.
    • The Contractor is responsible for design errors and all corrections and resubmissions at their own risk and cost.
    • The Employer may employ and pay others if the Contractor fails to comply with instructions, with costs borne by the Contractor.
    • The Contractor is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    More Like This

    R 2017 - 4
    37 questions

    R 2017 - 4

    AstoundedHamster avatar
    AstoundedHamster
    Ley 4/2017 sobre discapacidad
    21 questions
    ACCA DipIFR June 2017 Exam - IAS 40
    5 questions

    ACCA DipIFR June 2017 Exam - IAS 40

    SelfDeterminationHydrogen avatar
    SelfDeterminationHydrogen
    Use Quizgecko on...
    Browser
    Browser