What is the Contractor required to submit before the Tests on Completion?
What is the Contractor required to submit before the Tests on Completion?
When should the Contractor rectify errors or defects found in the provisional O&M Manuals?
When should the Contractor rectify errors or defects found in the provisional O&M Manuals?
In case of errors found in the Contractor's design and/or documents, how should they be corrected?
In case of errors found in the Contractor's design and/or documents, how should they be corrected?
When should the final O&M Manuals be submitted to the Employer?
When should the final O&M Manuals be submitted to the Employer?
Signup and view all the answers
Who is responsible for engaging and paying all personnel, their accommodation, transport, and welfare?
Who is responsible for engaging and paying all personnel, their accommodation, transport, and welfare?
Signup and view all the answers
What becomes the property of the Employer upon delivery to the site or payment to the Contractor?
What becomes the property of the Employer upon delivery to the site or payment to the Contractor?
Signup and view all the answers
In what circumstances can the Employer employ and pay others for the work with costs borne by the Contractor?
In what circumstances can the Employer employ and pay others for the work with costs borne by the Contractor?
Signup and view all the answers
Who is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials?
Who is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials?
Signup and view all the answers
What must the Employer give not less than 14 days before the Commencement Date?
What must the Employer give not less than 14 days before the Commencement Date?
Signup and view all the answers
Who is responsible for design errors and all corrections and resubmissions at their own risk and cost?
Who is responsible for design errors and all corrections and resubmissions at their own risk and cost?
Signup and view all the answers
What happens if Plant and/or Materials delivery is suspended for more than 28 days?
What happens if Plant and/or Materials delivery is suspended for more than 28 days?
Signup and view all the answers
Under what circumstances can the Contractor request permission to proceed if the suspension of work continues for more than 84 days?
Under what circumstances can the Contractor request permission to proceed if the suspension of work continues for more than 84 days?
Signup and view all the answers
What must the Contractor comply with regarding wages and labor conditions?
What must the Contractor comply with regarding wages and labor conditions?
Signup and view all the answers
Under what circumstances can the Employer employ and pay others for the work with costs borne by the Contractor?
Under what circumstances can the Employer employ and pay others for the work with costs borne by the Contractor?
Signup and view all the answers
What specific provision applies for suspension and evidence of compliance if the Contractor fails to comply with instructions?
What specific provision applies for suspension and evidence of compliance if the Contractor fails to comply with instructions?
Signup and view all the answers
Who is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials?
Who is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials?
Signup and view all the answers
What happens if the Employer does not give a Notice within 14 days after receiving the test results?
What happens if the Employer does not give a Notice within 14 days after receiving the test results?
Signup and view all the answers
What action can the Employer take if the Tests on Completion are unduly delayed by the Contractor?
What action can the Employer take if the Tests on Completion are unduly delayed by the Contractor?
Signup and view all the answers
What happens if the Contractor fails to carry out the Tests on Completion within the specified period?
What happens if the Contractor fails to carry out the Tests on Completion within the specified period?
Signup and view all the answers
What is the consequence if the Works fail to pass the Tests on Completion?
What is the consequence if the Works fail to pass the Tests on Completion?
Signup and view all the answers
What provision applies if the Works fail to pass the Tests on Completion and need to be repeated?
What provision applies if the Works fail to pass the Tests on Completion and need to be repeated?
Signup and view all the answers
What is the consequence if the Works fail to pass the Tests on Completion repeated under Sub-Clause 9.3 [Retesting]?
What is the consequence if the Works fail to pass the Tests on Completion repeated under Sub-Clause 9.3 [Retesting]?
Signup and view all the answers
What becomes of the repeated tests under Sub-Clause 9.3 [Retesting]?
What becomes of the repeated tests under Sub-Clause 9.3 [Retesting]?
Signup and view all the answers
What is the Employer entitled to if the Works fail to pass the Tests on Completion repeated under Sub-Clause 9.3 [Retesting]?
What is the Employer entitled to if the Works fail to pass the Tests on Completion repeated under Sub-Clause 9.3 [Retesting]?
Signup and view all the answers
What happens if the Tests on Completion are unduly delayed by the Employer's Personnel or due to a cause for which the Employer is responsible?
What happens if the Tests on Completion are unduly delayed by the Employer's Personnel or due to a cause for which the Employer is responsible?
Signup and view all the answers
Study Notes
FIDIC 2017 EPC/Turnkey Contract - Key Clauses Summary
- The Contractor is responsible for engaging and paying all personnel, their accommodation, transport, and welfare, unless otherwise stated in the Specification.
- The Contractor must comply with laws and standards for wages and labor conditions, and cannot recruit the Employer's personnel.
- If the Contractor fails to comply with instructions, the Employer may employ and pay others for the work, with costs borne by the Contractor.
- Plant and materials become the property of the Employer upon delivery to the site, payment to the Contractor, or as determined under specific sub-clauses.
- The Contractor is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials.
- The Employer must give a notice of the Commencement Date not less than 14 days before the date, unless otherwise stated in the Particular Conditions.
- The Contractor must complete the works within the agreed Time for Completion, with specific provisions for suspension and evidence of compliance.
- If Plant and/or Materials delivery is suspended for more than 28 days, specific conditions apply for marking and evidencing compliance.
- If the suspension continues for more than 84 days, the Contractor may request permission to proceed, and if not granted, may terminate the contract.
- The Contractor is responsible for design errors and all corrections and resubmissions at their own risk and cost.
- The Employer may employ and pay others if the Contractor fails to comply with instructions, with costs borne by the Contractor.
- The Contractor is responsible for paying royalties, rents, and other payments for natural materials obtained from outside the site and disposal of materials.