Podcast
Questions and Answers
A business analyst wants to know who to contact about a roadblock specific on a feature. Which tool will help them find the right contact?
A business analyst wants to know who to contact about a roadblock specific on a feature. Which tool will help them find the right contact?
- Work breakdown structure
- Responsible, accountable, consulted, and informed (RACI) matrix (correct)
- Stakeholder register
- Requirement traceability matrix
Given the following information, what is the schedule variance (SV) for this project?
Early start date (ES): 16 weeks
Actual time: 12 weeks
Schedule performance index (SPI): 1.3
Given the following information, what is the schedule variance (SV) for this project?
Early start date (ES): 16 weeks Actual time: 12 weeks Schedule performance index (SPI): 1.3
- 5
- 3
- 4 (correct)
- 2
A project veers off track due to scope creep. The project management team requests an immediate response from the major stakeholders.
What should the project manager do next to avoid project failure?
A project veers off track due to scope creep. The project management team requests an immediate response from the major stakeholders.
What should the project manager do next to avoid project failure?
- Adopt a change management approach and delay the project to decide on the direction.
- Delay the project by adopting a fast-fail approach, mitigating the risk of having a bigger impact on the company.
- Develop a focus group to face the issue and decide on the appropriate direction. (correct)
- Request a meeting with top management to state concerns about their ability to handle the station.
A project team has completed the first iteration, and the testing manager approved the test report, indicating that the acceptance criteria have been met. However, the manager of a business unit requests additional functionality before approving the rollout for their team.
What should the project manager do next?
A project team has completed the first iteration, and the testing manager approved the test report, indicating that the acceptance criteria have been met. However, the manager of a business unit requests additional functionality before approving the rollout for their team.
What should the project manager do next?
Why is a project undertaken?
Why is a project undertaken?
In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?
In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?
An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the stockholders' review of the product.
One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.
Why was the product still determined to be ready for delivery?
An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the stockholders' review of the product.
One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.
Why was the product still determined to be ready for delivery?
A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear.
What should the project manager do next?
A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear.
What should the project manager do next?
A project team is reviewing project performance. During the execution phase, the project team discovers that there is an off-the-shelf (OTS) product, which could reduce the time and cost of project delivery.
What should the project manager do next?
A project team is reviewing project performance. During the execution phase, the project team discovers that there is an off-the-shelf (OTS) product, which could reduce the time and cost of project delivery.
What should the project manager do next?
In adaptive projects, who should approve the prioritization of the backlog?
In adaptive projects, who should approve the prioritization of the backlog?
A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting.
Which two procedures will the project team perform? (Choose two)
A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting.
Which two procedures will the project team perform? (Choose two)
An adaptive team's velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it will take to complete the project.
How should the project manager calculate the anticipated velocity for future sprints?
An adaptive team's velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it will take to complete the project.
How should the project manager calculate the anticipated velocity for future sprints?
Which of the following is a goal of the project charter?
Which of the following is a goal of the project charter?
A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements first.
What should the business analyst do?
A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements first.
What should the business analyst do?
What is the equation to calculate cost variance (CV)?
What is the equation to calculate cost variance (CV)?
A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month. The project manager aims to maximize the return on investment (ROI) as the project runs from the first cycle.
Which methodology should the project manager adopt and implement in the project?
A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month. The project manager aims to maximize the return on investment (ROI) as the project runs from the first cycle.
Which methodology should the project manager adopt and implement in the project?
When would be the most appropriate time to address the issue raised on the iteration review?
When would be the most appropriate time to address the issue raised on the iteration review?
Calculate the schedule performance index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.
Calculate the schedule performance index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.
Flashcards
Stakeholder Register
Stakeholder Register
A document that lists all project stakeholders, their roles, and contact information.
Requirement Traceability Matrix
Requirement Traceability Matrix
A document that tracks requirements from their source to their implementation.
RACI Matrix
RACI Matrix
A tool that defines roles (Responsible, Accountable, Consulted, Informed) for each task.
Work Breakdown Structure
Work Breakdown Structure
Signup and view all the flashcards
Schedule Variance (SV)
Schedule Variance (SV)
Signup and view all the flashcards
Earned Value (EV)
Earned Value (EV)
Signup and view all the flashcards
Planned Value (PV)
Planned Value (PV)
Signup and view all the flashcards
Schedule Performance Index (SPI)
Schedule Performance Index (SPI)
Signup and view all the flashcards
Scope Creep
Scope Creep
Signup and view all the flashcards
Change Management
Change Management
Signup and view all the flashcards
Project Failure
Project Failure
Signup and view all the flashcards
Study Notes
No specific text provided. Please provide the text or questions for study notes.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.